Trade contractor
On construction management contracts, a construction manager is appointed on a consultancy and management basis to provide advice to the client during the pre-construction stages and then to manage the construction of the works. The works are divided into packages which are contracted to separate contractors. These contractors are referred to as trade contractors rather than sub-contractors (as they are contracted directly by the client, rather than being sub-contracted to the construction manager). The separate appointment of trade contractors should reduce the cost of contracts, as the management element is being provided by the construction manager. It also allows the advancement of some works (such as groundworks or piling) which might begin even before design of the above-ground works is complete.
Characteristics of trade contracts include:
- Trade contractors may be appointed through a single-stage procurement process, or through a two-stage process with a pre-construction services agreement for the first stage.
- Each trade contract must have its own separate practical completion certification and so they may have different defects liability periods. Certification cannot be dependent on completion of works outside of the scope of the contract. As trade contracts may be completed at different times, the construction manager must ensure that measures are in place to protect completed work from ongoing activities.
- Trade contracts (such as the Joint Contracts Tribunal (JCT) CM/TC 2011) do not include provisions for liquidated damages, instead the trade contractor indemnifies the client's direct loss and/or expense for lateness.
- Trade contracts may allow for retention, or may include a requirement for a retention bond.
- Trade contracts should include requirements to adopt collaborative practices.
- As there is no main contractor, trade contractors should provide master programmes for their works.
- Trade contractors should be required to provide regular information in relation to key performance indicators.
- Where they carry out design, trade contractors may be required to provide as-built drawings.
Notes
- On management contracts, contractors are known as 'works contractors'.
- For a detailed description of the sequence of tasks necessary on a construction management contract, see the work plan: construction management: outline work plan.
NB A trades contractor (with an 's') is a more general term which simply refers to a contractor who undertakes a particular class of construction work, such electrical installation. See Trades contractor for more information.
[edit] Related articles on Designing Buildings
- Back-to-back provisions in construction contacts.
- Collaborative practices.
- Collateral warranties.
- Construction manager.
- Construction contract.
- Contracting.
- Contractor.
- Contractors master programme.
- Main contractor.
- Management contract.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade body.
- Types of contractor.
- Works contractor.
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.