Trade contractor
On construction management contracts, a construction manager is appointed on a consultancy and management basis to provide advice to the client during the pre-construction stages and then to manage the construction of the works. The works are divided into packages which are contracted to separate contractors. These contractors are referred to as trade contractors rather than sub-contractors (as they are contracted directly by the client, rather than being sub-contracted to the construction manager). The separate appointment of trade contractors should reduce the cost of contracts, as the management element is being provided by the construction manager. It also allows the advancement of some works (such as groundworks or piling) which might begin even before design of the above-ground works is complete.
Characteristics of trade contracts include:
- Trade contractors may be appointed through a single-stage procurement process, or through a two-stage process with a pre-construction services agreement for the first stage.
- Each trade contract must have its own separate practical completion certification and so they may have different defects liability periods. Certification cannot be dependent on completion of works outside of the scope of the contract. As trade contracts may be completed at different times, the construction manager must ensure that measures are in place to protect completed work from ongoing activities.
- Trade contracts (such as the Joint Contracts Tribunal (JCT) CM/TC 2011) do not include provisions for liquidated damages, instead the trade contractor indemnifies the client's direct loss and/or expense for lateness.
- Trade contracts may allow for retention, or may include a requirement for a retention bond.
- Trade contracts should include requirements to adopt collaborative practices.
- As there is no main contractor, trade contractors should provide master programmes for their works.
- Trade contractors should be required to provide regular information in relation to key performance indicators.
- Where they carry out design, trade contractors may be required to provide as-built drawings.
Notes
- On management contracts, contractors are known as 'works contractors'.
- For a detailed description of the sequence of tasks necessary on a construction management contract, see the work plan: construction management: outline work plan.
NB A trades contractor (with an 's') is a more general term which simply refers to a contractor who undertakes a particular class of construction work, such electrical installation. See Trades contractor for more information.
[edit] Related articles on Designing Buildings Wiki
- Back-to-back provisions in construction contacts.
- Collaborative practices.
- Collateral warranties.
- Construction manager.
- Construction contract.
- Contracting.
- Contractor.
- Contractors master programme.
- Main contractor.
- Management contract.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade body.
- Types of contractor.
- Works contractor.
Featured articles and news
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.