Elemental bill of quantities
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor), that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers to allow them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities:
- Elemental bill of quantities.
- Work package bill of quantities.
- Work section bill of quantities.
The elemental breakdown structure undertakes measurement and description by group elements, with each group element forming a separate section of the bill of quantities, irrespective of the order of work sections in NRM 2. Group elements are sub-divided through the use of elements, which are further sub-divided by sub-elements, as defined by NRM 1: Order of cost estimating and cost planning for capital building works.
This structure can make it easier for the cost consultant to analyse contractors' tender prices and collect real-time cost data.
NRM 2 suggests that an elemental breakdown structure for a simple project might be:
- Bill No. 1: Preliminaries (main contract).
- Bill No. 2: Facilitating works.
- Bill No. 3: Substructure.
- Bill No. 4: Superstructure.
- Bill No. 5: Internal finishes.
- Bill No. 6: Fittings, furnishings and equipment.
- Bill No. 7: Services.
- Bill No. 8: External works.
- Bill No. 9: Risks.
- Bill No. 10: Provisional sums.
- Bill No. 11: Credits.
- Bill No. 12: Daywork (provisional).
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental cost plan.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Schedule of rates.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Unpriced bill.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
A call for prevention and sensitive re-use.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
BSA residential sector competence standards guidance
BSAS 01:2024 Organisational Capability Management System Standard - Competence Assurance.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
Comments