Management contracting - pros and cons
Management contracting is a procurement route in which the works are constructed by a number of different works contractors who are contracted to a management contractor. The management contractor is generally appointed by the client early in the design process so that their experience can be used to improve the cost and buildability of proposals as they develop, as well as to advise on packaging and the risks of interfaces.
The agreement between client and management contractor is likely to cover both pre-construction and construction activities, with a notice to proceed between the two, before which works contracts cannot be let.
For more information see: Management contracting.
Management contracting can be beneficial on complex and/or specialist projects made up of a number of packages individually appointed to the best-suited subcontractor. This means that there is the potential for the highest-quality of delivery.
It can also be beneficial for the client in that they are able to retain control of the design while drawing on the experience and expertise of a construction specialist as part of the professional team, since the management contractor contributes to the design process. At the same time, the client is able to move risks or procurement and delivery onto the management contractor who is responsible both for project management and carrying out the works.
In addition, rather than the contractor tendering a fixed price, they can provide cost savings for the client, as well as time savings by tendering some of the work packages early (such as groundworks) and overlapping the design and construction activities. This allows for a quick start on site.
There can be also be considerable flexibility in the design, with changes being made throughout the construction process (albeit with potential cost implications).
However, it can be unsuitable as a procurement route for inexperienced clients since, although they can have more control over the design, works usually begin before the nature of the completed building is known. The lack of available specialists may also cause unproductive gaps in the work to be undertaken.
There is a body of opinion that believes that if a management contractor operating on a cost plus fee arrangement pursues a works contractor in court for non-performance, the management contractor is unable to prove loss and damages. This is because the loss is simply passed on to the client, and so it is the client that has incurred the damage. This has increased the tendency for clients to require direct warranties from each works contractor.
A decision needs to be made as to whether the client wishes to retain the services of both an independent cost consultant or to transfer cost planning, reporting and cost control as a service to be provided by the management contractor. A judgement has to be made on the competence and experience of the management contractor's proposed quantity surveying and cost estimating team and whether the client has a competent individual to police the financial aspects of the management contractor’s consultancy agreement.
[edit] Related articles on Designing Buildings
- Construction contract.
- Construction management contract.
- Design and build - pros and cons.
- Design build operate (DBO).
- Design liability.
- Employer’s requirements.
- Management Building Contract.
- Management contract: outline work plan.
- Management contractor.
- Traditional contract - pros and cons.
- Works contractor.
Featured articles and news
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Home improvements swapped for green energy upgrades
As applications down since and desire to reduce bills up.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
The Use of Natural Insulation Materials in Retrofit
New paper from STBA with support from SDF.
National Retrofit Hub in partnership with InstallerSHOW.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Biodiversity and the built environment digital series
The nature of building, with CIOB and CWP.
A call for prevention and sensitive re-use.
Risks to the long-term effectiveness of the BNG scheme
National Audit Office publish review of Biodiversity Net Gain.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
Comments