[edit] Introduction
On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider (Operation and Maintenance) is often appointed late in the project.
This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before practical completion (PC) gives the contractor, supply chain and O&M provider little time to manage the task properly. Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.
[edit] Issues with late engagement
- Added cost for O&Ms not previously budgeted for.
- Trades already left site and fully paid.
- No standardisation across O&M submissions.
- Increased pressure on site teams close to PC.
- Risk of missing or incomplete O&M submissions.
- Unhappy end client.
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.
O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.
The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.
[edit] Benefits of early engagement
- Cost certainty – a realistic budget for O&Ms in the cost plan.
- O&M templates in contract documents.
- Free up valuable site resource.
- Trades managed as and when they start on site.
- Plenty of time to conduct a thorough O&M review.
- Smooth, pain free handover at PC.
- Happy client with a complete and accurate as-built record.
Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as-built record at PC.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.