Early appointment of O&M providers
Contents |
[edit] Introduction
On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider (Operation and Maintenance) is often appointed late in the project.
This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before practical completion (PC) gives the contractor, supply chain and O&M provider little time to manage the task properly. Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.
[edit] Issues with late engagement
- Added cost for O&Ms not previously budgeted for.
- Trades already left site and fully paid.
- No standardisation across O&M submissions.
- Increased pressure on site teams close to PC.
- Risk of missing or incomplete O&M submissions.
- Unhappy end client.
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.
O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.
The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.
[edit] Benefits of early engagement
- Cost certainty – a realistic budget for O&Ms in the cost plan.
- O&M templates in contract documents.
- Free up valuable site resource.
- Trades managed as and when they start on site.
- Plenty of time to conduct a thorough O&M review.
- Smooth, pain free handover at PC.
- Happy client with a complete and accurate as-built record.
Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as-built record at PC.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.


















