Early appointment / involvement
Contents |
[edit] Introduction
Early appointment typically refers to the involvement at the earliest possible stage in the design process of certain stakeholders to a construction project, with the aim of fostering partnering and improved team working. This will help ensure a project environment that manages risk, encourages innovation, improves collaboration, is less adversarial, and minimises unforeseen costs and delays – all of which can help deliver value for money.
[edit] Contractor
Early contractor involvement (ECI) allows contractors to participate in both the design development and construction planning stages. This can be essential for some projects, especially very large or complex projects and particularly those that rely on building information modelling (BIM), or where speed it important.
ECI clauses are now part of NEC contracts which are published by the Institution of Civil Engineers (ICE). A single NEC3 Engineering and Construction Contract (ECC) can be used for both stages where contractors are participating. ICE has suggested that early contractor involvement “...supports improved team working, innovation and planning to deliver value for money”.
ECI allows the contractor to input contractual, construction and design experience and ideas at an early stage in consultation with the client, architect, engineer and other consultants. In so doing, the contractor can influence the design in a beneficial way, advise on constructability, cost estimating, in-use performance, construction sequencing, materials and lead times, site considerations and a host of other matters that the client and other consultants may not have as much experience of. This means the contractor becomes familiar with the project over a longer period of time and can help avoid costly mistakes and delays.
The client (or employer) can appoint the contractor to help its consultants with the project design or to design specific elements. This is normally followed by the contractor being asked to deliver the works. Alternatively, the client can appoint the contractor to deliver the design helped by the client’s consultants.
For more information see: Early contractor involvement.
[edit] Key sub-contractors and suppliers
Early involvement of key sub-contractors and suppliers in the design process can also have benefits for a project such as establishing market pricing for the work involved, contributing to the design process, developing long lead time items and so on. This can also help the client, sub-contractors, suppliers and main contractor mitigate risk.
[edit] Other stakeholders
Community ‘buy-in’ (local residents, businesses, politicians and community groups and so on) at an early stage in a construction project can result in benefits for a project. Informed stakeholders that are part of the dialogue can enhance a project, avoiding potentially disruptive community relations and bad publicity. An involved community will more likely lend its support to a project.
Educating the community about a project’s goals is based primarily on providing information and inviting dialogue at workshops, meetings and other events which:
- Allow the community to generate ideas for project planning and implementation;
- Helps establish project sustainability and discovers what the community thinks and needs;
- Improves community relations and
- Gives the community a sense of empowerment that fosters acceptance.
For more information see: Stakeholder management.
[edit] Related articles on Designing Buildings Wiki
- Collaborative practices.
- Construction contract.
- Contract conditions.
- Contractor's design portion.
- Defined cost.
- Delay damages.
- Early contractor involvement.
- Institution of Civil Engineers.
- JCT.
- Latham Report
- Management contract.
- NEC contract change management systems.
- NEC3.
- Optimised contractor involvement.
- Procurement route.
Featured articles and news
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”























