When to install a staircase during the construction process
Installing a staircase too early in a build process exposes it to the risk of damage. Particularly with high-end staircases, from sweeping helical stairs to spiral staircases made with exposed solid hardwood, installing a stair in an ongoing building environment increases the risk of damage due to builders and tradesmen frequently using it.
With anything bespoke or custom made, ordering a staircase comfortably ahead of schedule is the best course of action. Leaving it too late can cause pressure and undue stress which could lead to mistakes in measuring, drawing or production.
The measurements must be complete, accounting for any floor finishes, architraves, radiators window sills etc. These dimensions need to be taken as late as possible to allow for one final draft of drawings before production. The earlier the site measurements are taken, the further they will be from the finished build.
Generally, it is better for a staircase to be one of the last items to be installed – perhaps a few days before the property is occupied. The walls should be plastered and painted and the finished floors laid – certainly downstairs.
Some builders like the staircase fitted halfway through the build, but this is mainly so they do not have to use ladders. They are probably also more familiar with conventional timber staircases which will later be carpeted. Simply protecting the treads will not be sufficient. A visibly protected stair might actually encourage people to use it and cause damage.
Communication and planning is the key to any successful project. Keep in mind that the original date for the stair install might well shift due to other delays with the build, so be prepared to alter it accordingly and keep the staircase company informed.
[edit] Related articles on Designing Buildings Wiki
- Stairs.
- Approved Document K.
- Maximum length of a flight of stairs.
- Protected stair v escape stair.
- Approved Document B.
- Protected stairway.
- Landings in buildings.
- Stairs riser.
- Means of escape.
- Types of stairs.
- Width of doors stairs and escape routes.
- Spiral stairs and helical stairs.
- Approved Document M.
- Stairs going.
- Stairs tread.
- Railings.
- Accommodation stair.
- Stairs nosing.
- Guarding.
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.