[edit] What is blinding in construction?
In construction, 'blinding' typically refers to a base layer of weak concrete or sand that is laid above a layer of hardcore to provide a clean, level and dry working surface. A thin layer, usually around 50 mm (2 inches) thick, of blinding is poured over the hardcore, sealing in the underlying material and levelling off the surface.
The concrete used for blinding is weak compared with structural concrete, and can withstand lower loading. If necessary, steel mats can be used to reinforce either the entire blinding layer or the specific areas of high loading.
[edit] What is blinding for?
If a damp-proof membrane (DPM) is to be placed above it, the blinding will help prevent it from becoming damaged by the hardcore.
If a damp-proof membrane is not being laid directly above the blinding layer, it provides a sturdy surface on which a pavement, concrete floor, footing, raft foundation or reinforcement can be positioned, and it prevents the concrete from seeping down into the hardcore. It also reduces the amount of moisture penetrating up into the concrete.
A blinding layer can also provide a more useable working surface on construction sites, it creates a cleaner and more even site and provides a suitable ground for the storage of materials.
[edit] Alternative definitions of blinding
NB Culvert, screen and outfall manual, (CIRIA C786) published by CIRIA in 2019, gives an alternative definition of blinding as: ‘A temporary accumulation of impermeable debris on the lower part of a screen that creates a ‘weir’ effect, reducing the flow area and increasing upstream water levels. Preferred term is variable blockage.’ Where a screen is: ‘An arrangement of bars, grids or poles placed in a watercourse.’
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
ECA responds to the Milburn Report
Youth employment to be linked to workforce demand.
The construction industry urgently needs to attract new talent
CIOB responds to Neets report.
Grenfell Tower community update
Memorial columns to be retained as careful dismantling continues.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.

















Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.