Public project: feasibility studies
The feasibility studies stage considers the options for satisfying the client's needs, enabling them to prepare a business case for the preferred option and deciding whether to proceed with the project. It is possible to make an outline planning application during this stage if the risk to the project of not receiving planning permission is very high, or if delays in receiving planning permission would be problematic.
Depending on how experienced the client is, they may appoint external consultants such as independent client advisers or a project manager to assist them. This means that some of the tasks attributed to the client below might actually be carried out by independent client advisers or a project manager and vice versa.
Contents |
[edit] Appointing independent client advisers.
The client updates the preliminary business case and strategic brief to reflect comments made at the end of the previous stage and collates site information ready to issue to the independent client advisers.
The client appoints independent client advisers and if necessary a project manager. Go to work stage: Public project: appointment. NB The role of project manager can be performed by in-house personnel, or may be taken on by the project sponsor if they have the relevant experience.
The client chairs a start-up meeting to issue information to new appointments (such as the strategic brief and site information). This meeting is also an opportunity to establish collaborative practices and agree a programme.
[edit] Developing the strategic brief.
The independent client advisers work with the client to help them develop the strategic brief sufficiently for feasibility studies and options appraisals to be carried out.
The independent client advisers assess the site information issued to them by the client and undertake site appraisals. The independent client advisers obtain any further information about the site that might be required to undertake feasibility studies, such as; site surveys, information about site services, site access conditions, legislative constraints, existing planning consents etc. Where necessary, approval should be sought from the client (for example site surveys requiring additional expenditure).
The independent client advisers co-ordinate the preparation of feasibility studies to establish whether the project is viable, and to identify feasible options. The client considers the feasibility studies, and agrees which options the independent client advisers should develop.
[edit] Preparing an options review report.
The independent client advisers co-ordinate the identification of any further site surveys or site information required in order to carry out options appraisals and where appropriate seek approval from the client.
The independent client advisers prepare options studies with a view to drafting an options review report.
The independent client advisers and the client prepare for and enter into consultations with the local authority and other statutory authorities and assess possible planning permission requirements and other statutory requirements (such as the need for an environmental impact assessment for the options). NB See the work stage: Public project: planning permission for additional information.
The independent client advisers prepare initial cost appraisals of the options.
The independent client advisers co-ordinate the preparation of a draft options review report.
The client considers the draft options review report and either selects a preferred option or instructs the independent client advisers to revise the options review report.
[edit] Preparing a business case and project execution plan.
The independent client advisers co-ordinate further assessment of the preferred option to assist the client in preparing the business case and project execution plan, including:
- Establishing the requirements for statutory approvals and other regulations with which the preferred option must comply.
- Entering into consultations with utility providers.
- Assessing the need for additional specialist advice and advise the client.
With the benefit of assessments carried out by the independent client advisers, the client develops a business case and project execution plan for the preferred option.
The client considers, and if appropriate approves the business case and project execution plan for the preferred option and gives instructions to proceed to the next stage along with any other instructions that may be necessary.
Once it has been decided that the project will progress to the next stage, the client places (or arranges to have placed) all necessary OJEU or other advertisements.
At this stage, the client and the independent client advisers may consider whether it would be appropriate to make an outline planning application for the proposed development. It can be important that the planning parameters for the project and, where appropriate, outline planning consent are obtained prior to tender, as any changes to the project resulting from the planning permission process after the integrated supply team has been appointed may prove expensive for the client and can cause significant delays. If an outline planning application is required, go to the work stage: Public project: planning permission.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.