Public project: planning permission
Planning permission is a vitally important part of almost all projects, often making the difference between whether the project proceeds to design or not. Many clients will be unwilling to commit to paying fees for detailed design until they have received planning permission, and on particularly high risk projects, the client may wish to obtain outline planning permission before committing to significant expenditure. As a consequence planning permission can be applied for at different stages of the project's development.
On public projects it is particularly important to establish where the risk lies for planning permission, and whether it is best left with the client or the integrated supply team. The client should at least consult the local planning authority to establish the likely planning parameters for the project, and perhaps seek a screening opinion as to whether an environmental impact assessment will be required before seeking bids. The client may wish to obtain outline planning permission before tendering, or even to make the contract conditional upon detailed planning permission being received. This means that whilst we have attributed preparing a planning application to the integrated supply team, some of the tasks described below may in fact be carried out by the client or their advisers.
Contents |
[edit] Assessing the type of application.
The integrated supply team considers the need for an outline planning application or detailed planning application (if no previous applications have been made by the client), and if appropriate begins to prepare an application.
The integrated supply team considers the likely need for an environmental impact assessment. If necessary they may seek a screening decision and or a scoping studt from the local planning authority. If necessary, the integrated supply team prepares or arranges for the preparation of an environmental impact assessment.
[edit] Undertaking a consultation process.
The integrated supply team consults with the local planning authority (and other appropriate statutory and non-statutory authorities) to determine the preferred form of the application, dates of planning committee meetings, committee procedures, possible planning conditions and possible planning obligations (section 106 agreement), the community infrastructure levy and the requirement to undertake an external consultation process.
The integrated supply team considers the cost effects of statutory requirements and other requirements including possible planning conditions and planning obligations (section 106 agreement) and if necessary, amends the design.
The integrated supply team discusses with the client the extent and nature of any external consultation process that will be undertaken and then begins the consultation. They then consider the results of the process and carry out further revisions to the design if required.
[edit] Preparing a planning application.
The integrated supply team co-ordinates the preparation of a draft planning application and issues this to the client for comment.
The integrated supply team considers any abnormal costs arising from the draft planning application, and If necessary, arranges a value management exercise and amends the outline or detailed planning application.
[edit] Submitting a planning application.
The integrated supply team submits the planning application including the planning fee.
The integrated supply team consults with the local planning authority on the progress of the application and likely planning conditions and planning obligations (section 106 agreement). They then bring these to the attention of the client and if necessary revise the application (there may be conditions or obligations that will impact on the client's operation of the development).
If necessary, the client and integrated supply team respond to questions from the local planning authority and make representations to the planning committee.
On receipt of a decision (or likely decision recommended by the officers' report) the client and integrated supply team consider the planning conditions and and planning obligations (section 106 agreement) that have been (or are likely to be) imposed, and if necessary revise the application.
If required, the integrated supply team revises and re-submits the planning application.
If necessary, on receipt of the decision the integrated supply team lodges an appeal.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.