Party wall notice response options
Contents |
[edit] Introduction
A neighbour may serve you with a Party Wall Notice with regards to upcoming construction work. For example, a building owner may want to build an extension, amend/modify the structure of a party wall or may work close to a building’s foundation. A building owner may even serve you with a notice if they need to carry out excavations near neighbouring buildings.
In this scenario, you have three options. You may ignore the notice, you may agree or you may dissent/disagree. There are consequences of all these actions:
- Your neighbour may consult with you with regards to this issue or may appoint a party-wall surveyor if you do not reply to the notice.
- You have to sign the ‘acknowledgement’ letter that is enclosed together with the party wall notice if you agree to the notice. Signing this letter attests to the fact that you agree to the construction work.
- A formal dispute between you and your neighbour will start if you disagree. Your neighbour may appoint a party-wall surveyor to resolve the issue. You also have the right to appoint a surveyor in order to represent your interest.
According to the Party Wall etc. Act 1996, you will be identified as an ‘adjoining owner’ as you received the notice and your neighbour is identified as the building owner as they served you with the notice.
[edit] Appointing solicitors
If you dissent/disagree with the construction work outlined in the party wall notice then you may appoint a solicitor to represent your interests in the dispute. You may appoint a qualified and experienced party-wall surveyor instead of appointing a solicitor.
[edit] Consenting to construction work
The simplest option after being served with a notice is to consent to the construction work outlined in it. If you agree to the notice, then you are permitting the building owner to move forward with the proposed construction works within the specified timeline.
It is not uncommon for an adjoining owner to receive an incorrectly drafted notice or letter. A notice being served to an adjoining owner may be invalid due to a technicality. The construction work is not supposed to start until the flawed notice has been corrected and redrafted and has been reserved on all affected parties.
[edit] Consenting with conditions
If you want additional construction work to be undertaken on the party wall alongside the proposed construction work by a building-owner, then it is essential for you to serve a ‘counter-notice’.
According to the Party Wall Act 1996, an adjoining owner has the legal right to ask for an amendment to the proposals. However, you have to make a financial contribution to the construction project if this amendment benefits your property. A ‘building-owner’ is allowed to consider this request. They may seek the advice of a surveyor to ensure that this request is permitted by the Party Wall Act or to learn about the impact of this amendment on their property.
You may ask an appointed party-wall surveyor to record the condition of your property in writing and to collect photographs of the property as evidence prior to starting the construction work.
[edit] Dissenting from construction work
It is possible to delay a construction project if you sign the acknowledgement notice as disagreeing to the work. It informs a building owner regarding your objection and they may try to resolve this issue through a discussion with you or may appoint a party-wall surveyor. You may propose to appoint a surveyor to represent your own interests.
A building owner is supposed to pay the consultation fees of all appointed surveyors. However, in exceptional circumstances, an adjoining owner is supposed to pay the consultation fee of the party wall surveyor who represents their interest in the party wall dispute.
[edit] Ignoring the party wall notice
Nothing is gained from ignoring a party wall notice, as it will turn into an automatic dissent/dispute after a few days. However, this process protects an adjoining owner if they are away from home for a few days and cannot learn about the notice until their return.
[edit] Agreed surveyor
It is prudent to work with an agreed surveyor if a building owner is going to perform simple construction work. For example:
- Altering/rebuilding/repairing a party chimney stack on the roof.
- Cutting out and replacing the damaged bricks of a shared parapet wall that rises above the roof level.
It is also prudent to work with separate party-wall surveyors if there is complex construction work (piling, opening-up a structure, deep excavations) or if a surveyor has to monitor the structure during construction.
Each party is supposed to formally appoint a surveyor within a specified timeline and both surveyors work together in order to reach a party wall agreement that is known as a ‘Party Wall Award’.
[edit] About this article
This article was provided by Berrylodge in January 2020.
[edit] Related articles on Designing Buildings Wiki
- Adjoining buildings definition.
- Appointing consultants.
- Basement excavation.
- Building an extension.
- Conversion.
- De minimis.
- Derogation from grant.
- Fence.
- Line of junction notice.
- Load-bearing wall.
- Neighbour.
- Party structure notice.
- Party wall surveyor.
- Preventing wall collapse.
- Responsibility for boundary features.
- Right of support.
- Statutory approvals.
- Statutory authorities.
- Three party wall notice responses.
- Trespass.
- Wall types.
- What approvals are needed before construction begins.
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.