Party wall dispute
A dispute in the Party Wall sense of the word need not be much of a dispute at all; even if the Act says it is. Under the Party Wall etc. Act 1996, if an adjoining owner doesn’t consent within 14 days of receiving notice of the proposed works then the parties are deemed to be “in dispute”. The way that disputes under the Act are resolved is by each of the owners appointing a surveyor and those surveyors agreeing the terms of Party Wall Agreement.
Even if the adjoining owner decides to concur with their neighbour’s choice of surveyor as “agreed surveyor” (normally a good decision for minor works) there is still a “dispute” to be resolved so an award must be drawn up and served on the owners.
In effect, what an adjoining owner is saying when they instigate a dispute is that they would like to have their interests protected by a person who understands construction matters and is familiar with the procedures under the Party Wall Act.
It could not be easier for an adjoining owner to instigate a dispute; they need do nothing at all. If Party Wall Notices and Notices of Adjacent Excavation are not consented within 14 days of being received then a DISPUTE has arisen.
The adjoining owner may appoint a surveyor (or concur in the appointment of an agreed surveyor) within the 14 day period but they needn’t rush their decision. Once the 14 days have elapsed they must be sent a follow-up letter asking them to appoint a Party Wall Surveyor within 10 days or risk one being appointed on their behalf by the building owner (the party planning the work). If a building owner does gain the right to appoint a surveyor on behalf of their neighbour that cannot be the same surveyor that they are using; an Agreed Surveyor cannot be appointed unless both owners confirm that appointment in writing.
Once a dispute has arisen both the building owner and the adjoining owner change from being “clients” to “appointing owners” - the terminology reinforces the surveyor’s duty to be impartial. A surveyor can serve notice on behalf of their client because at that stage it is not known whether the adjoining owner will consent or not. If they consent there will be no award and no need for a party wall surveyor.
[edit] Related articles on Designing Buildings Wiki
- 10(4) Party Wall Surveyor Appointments.
- Adjoining buildings definition.
- Adjoining owner.
- Fence.
- Institute of party wall surveyors.
- Line of junction notice.
- Party structure notice.
- Party Wall Act.
- Party wall surveyor.
- Preventing wall collapse.
- Responsibility for boundary features.
- Right of support.
- Trespass.
- Wall types.
- What approvals are needed before construction begins.
- Who Pays for Party Wall Surveyor's Fees?
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.