Most Economically Advantageous Tender (MEAT)
[edit] Introduction
The Most Economically Advantageous Tender (MEAT) is a method of assessment that can be used as the selection procedure, allowing the contracting party to award the contract based on aspects of the tender submission other than just price.
MEAT was introduced by the European Parliament in January 2014. The European Union Procurement Directives established public procurement rules that apply to any public purchases above defined thresholds, and these are enacted in the UK by The Public Contracts Regulations.
The ‘alternative’ criteria which can be used in a MEAT assessment include:
- Quality.
- Price or cost using a cost-effectiveness approach.
- Technical merit.
- Aesthetic and functional characteristics.
- Accessibility.
- Social characteristics.
- Environmental characteristics.
- Innovative characteristics.
- After-sales service and technical assistance.
- Delivery conditions such as date, process and period.
Each of the criteria used is given a relative weighting, which must be set out in the tender documents. Alternatively, they can be listed in descending order of importance.
The rules stipulate that the contract notice must make clear to tenderers that the MEAT criteria will be used to judge their submission. The criteria cannot then be changed.
A two-stage process of tender evaluation can then be used. The first stage is a technical evaluation which uses individual weighted criteria to assess the technical merit of the tenders. The second stage is a financial evaluation which calculates the relative cost of each tender compared to the lowest price offered. Finally, the tenders are ranked based on the aggregate score of both stages.
[edit] Post Brexit reform
On 15 December 2020, the Green Paper Transforming Public Procurement was presented to Parliament by the Cabinet Office and Lord Agnew, the Minister of State for Efficiency and Transformation. The paper proposed several changes to procurement policy in the UK to reflect the country’s post-Brexit status.
During the UK’s membership of the EU, MEAT public procurement rules applied to any public purchases above defined thresholds and were overseen in the UK by the Public Contracts Regulations (PCR). Post-Brexit recommendations in the Transforming Public Procurement green paper proposed the replacement of MEAT procurement rules with MAT, essentially removing the ‘economic’ component from the method of assessment.
The thought process behind this modification was the idea that ‘economic’ could sometimes be interpreted simply as lowest price. Under MEAT, evaluating certain economic factors (such as quality) was seen as complex and potentially restrictive.
For more information see: Most advantageous tender.
[edit] Related articles on Designing Buildings
Featured articles and news
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.
Reslating an ancient water mill
A rare opportunity to record, study and repair early vernacular roofs.
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.























Comments