‘Flight’ is a term used in building design and construction to denote a continuous sequence of steps (or risers) connecting floors, landings or intermediate landings. The typical width of a flight in a domestic setting is around 850mm or more.
The arrangement and number of flights in a staircase will depend on the type of stair.
A ‘straight flight’ will have no intermediate landings and comprise a continuous series of risers between floor levels. See note below on maximum allowable risers in a flight.
A quarter-turn stair (sometimes called a ‘dog-leg’ stair) features a quarter-turn landing situated between flights. This may be located at any point on the staircase, from which point the second flight changes direction by 90 degrees to the left or right leading to the next floor above. In properties where space is at a premium, the landing may be replaced by a series of winders (wedge-shaped steps in plan) which then makes the stairway a continuous single-flight stair.
A half-turn stair usually involves a half landing between two flights and allows a 180-degree change of direction. An alternative arrangement to achieve 180-degree travel, space permitting, is to have two quarter landings in a configuration of flight-QL-flight-QL-flight; this may also form an open-well stair.
Whether a quarter- or half-turn stair, the flights can be supported on the landings.
The Approved Documents of the Building Regulations set out additional guidance and require compliance with various criteria concerning flights.
[edit] Length of flight
Stairs with more than 36 risers in consecutive flights should have at least one change in direction between flights. For buildings other than dwellings, the maximum number of risers between landings should be 16 for utility stairs and 12 for general access stairs. There should not be any single steps.
There are more complex requirements for tapered, spiral, alternating tread and helical stairs. Refer to Approved Document K.
For more information see: Landings in buildings and Maximum length of a flight of stairs.
[edit] For all buildings
At the top and bottom of every flight, landings should be provided which have a width and length at least as great as the smallest width of the flight.
Full requirements for flights and stairs generally can be found in the following Approved Documents:
- Approved Document B – Fire safety.
- Approved Document K – Protection from falling, collision and impact.
- Approved Document M – Access to and use of buildings.
[edit] Related articles on Designing Buildings Wiki
- Accommodation stair
- Approved Document B
- Approved Document K
- Approved Document M
- Firefighting lobby
- Guarding
- Ladder.
- Landings in buildings
- Maximum length of a flight of stairs
- Means of escape
- Protected stair v escape stair
- Protected stairway
- Railings
- Spiral stairs and helical stairs
- Stair design
- Stairs going
- Stairs nosing
- Stairs riser
- Stairs tread
- Types of stairs
- When to install a staircase during the construction process.
- Width of doors stairs and escape routes.
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.