Early appointment of O&M providers
Contents |
[edit] Introduction
On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider (Operation and Maintenance) is often appointed late in the project.
This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before practical completion (PC) gives the contractor, supply chain and O&M provider little time to manage the task properly. Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.
[edit] Issues with late engagement
- Added cost for O&Ms not previously budgeted for.
- Trades already left site and fully paid.
- No standardisation across O&M submissions.
- Increased pressure on site teams close to PC.
- Risk of missing or incomplete O&M submissions.
- Unhappy end client.
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.
O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.
The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.
[edit] Benefits of early engagement
- Cost certainty – a realistic budget for O&Ms in the cost plan.
- O&M templates in contract documents.
- Free up valuable site resource.
- Trades managed as and when they start on site.
- Plenty of time to conduct a thorough O&M review.
- Smooth, pain free handover at PC.
- Happy client with a complete and accurate as-built record.
Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as-built record at PC.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.