Construction management: production information
This stage is concerned with preparing the information that the trade contractors will need to construct the project. It should also include the completion of applications for statutory approvals. In this work plan we suggest the construction manager is appointed on completion of concept design. Earlier or later appointment will result in some activities being re-allocated between the consultant team and the construction manager (for example the role of cost consultant).
[edit] Starting the work stage.
The lead consultant co-ordinates a work stage start-up meeting with the client, construction manager and the consultant team to pass on feedback from the previous stage and agree the programme for the preparation of production information, along with its format, identification of work packages, sequencing and co-ordination procedures, including co-ordinating and integrating information from specialist trade contractors.
There should be a particular emphasis on equipment with long manufacturing times such as switchgear, chiller units, lifts, escalators and bespoke cladding systems, some of which may justify early ordering. The front-end construction work of service diversions, demolition, setting out, underground drainage, piling and groundworks may merit placing of preliminary contracts.
[edit] Agreeing tendering and construction procedures
The construction manager instigates discussions with the client regarding tendering and construction. Discussions might include:
- The possible use of preliminary contracts (for works such as ground exploration, demolition, decontamination or site clearance).
- The possibility of ordering long-lead items (such as switchgear, transformers, or booking piling rigs).
- The form of contract and contract conditions for works contracts (if this has not already been agreed).
- The nature of warranties and performance bonds that will be required from trade contractors.
- Exclusions from the contract.
- The date of possession and any phasing requirements.
- Tender procedures and the tender period.
- Any client contributions required for the contract documents.
- Insurance of the works.
- The need to appoint site inspectors.
- The need to appoint party wall surveyor(s) or rights of light surveyors.
[edit] Preparing production information and completing statutory approvals.
The lead designer prepares a schedule of production information, responsibilities for its preparation, a programme for its preparation and a document control system for version control.
The lead designer co-ordinates:
- The preparation and integration of production information. Any gaps in this information that will require specialist input after a tender process should be clearly defined, showing abutment details to adjacent work faces and how such work is integrated into the overall scheme.
- The preparation of schedules of inspections and tests, mock ups and samples.
- The preparation of a draft building user's guide and a building log book.
- The establishment of quality control systems and setting out criteria.
- Outstanding information needed for building regulations and other statutory approvals (such as negotiations with the Highways England, structural calculations, CO2 emission rate and a list of specifications used in the CO2 emission rate calculations) which must be submitted before works start on site.
The consultant team or construction manager may prepare or develop the site waste management plan if required.
The lead designer, consultant team and construction manager undertake a design review of the production information and make amendments or additions as necessary.
The construction manager develops the draft preliminaries document, draft tender documents and proposed contract conditions for the trade contracts (including relevant pre-construction services) and assesses any changes relative to the approximate quantities cost plan.
The lead consultant co-ordinates the preparation of a production information report for the client including any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
The construction manager and client should ensure that relevant party wall notices have been served.
The client considers the production information report and if necessary issues instructions to the lead consultant regarding changes required.
Featured articles and news
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.