Thickening claims
|
At its simplest, thickening is a contribution to a claimant’s increased overheads resulting from a client-culpable delay. Thickening is a legal term used in claims when claimants are legally entitled to claim extra costs – over and above the direct costs they may be already claiming – as a result of a delay which is outside their control.
For example, where an extension of time is granted to a contractor, they may also be entitled to claim for time-related costs for the delay period, in other words, in addition to the claim for direct costs, they may also be able to claim for ‘thickened’ overheads resulting from client/employer culpable delay or disruption.
In thickening claims, the claimant must, for example, prove that their head-office overheads had ‘thickened’, i.e. had increased, as a result of the defendant’s breach.
A celebrated case of thickening from October 2016 was that between contractor Flour, which had been engaged to construct an offshore wind farm, and steel fabricator ZPMC. Cracking had occurred in the welding of the steel monopoles and the transition pieces of the turbines for which the court held ZPMC to be in breach of contract. Damages of £15m and €7m were awarded to Fluor as part of direct costs caused by the breach and included costs of additional project management staff, consultants’ costs for the remedial works and costs for extra plant and equipment, as well as for providing extra storage space.
However, in addition, Fluor also claimed for ‘thickening’ costs amounting to 4% of the award – comprising overheads to reflect the increased head-office costs that were necessitated as a result of dealing with the breach of contract. Fluor argued that the thickening costs were just as much a result of the breach as were the direct costs.
The landmark case introduced the concept that certain overhead costs can be linked to a breach of duty just as if they were ordinary losses, i.e. direct losses that include items such as new materials, extra labour and consultant costs necessitated by the breach.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Adversarial behaviour in the UK construction industry.
- Alternative dispute resolution.
- Arbitration.
- Causes of construction disputes.
- Civil procedure rules.
- Conflict avoidance.
- Contract sum.
- Contractual right.
- Construction contract.
- Dispute resolution.
- Dispute resolution boards.
- Disruption claims in construction.
- Expert witness.
- Extension of time.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- How to prepare a claim for an extension of time.
- Litigation.
- Liquidated damages.
- Loss and expense.
- Mediation.
- Modifying clauses in standard forms of contract.
- Notice.
- Preliminaries.
- Scheme for Construction Contracts.
- Variation.
- What is a default?
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.






















