Thickening claims
|
At its simplest, thickening is a contribution to a claimant’s increased overheads resulting from a client-culpable delay. Thickening is a legal term used in claims when claimants are legally entitled to claim extra costs – over and above the direct costs they may be already claiming – as a result of a delay which is outside their control.
For example, where an extension of time is granted to a contractor, they may also be entitled to claim for time-related costs for the delay period, in other words, in addition to the claim for direct costs, they may also be able to claim for ‘thickened’ overheads resulting from client/employer culpable delay or disruption.
In thickening claims, the claimant must, for example, prove that their head-office overheads had ‘thickened’, i.e. had increased, as a result of the defendant’s breach.
A celebrated case of thickening from October 2016 was that between contractor Flour, which had been engaged to construct an offshore wind farm, and steel fabricator ZPMC. Cracking had occurred in the welding of the steel monopoles and the transition pieces of the turbines for which the court held ZPMC to be in breach of contract. Damages of £15m and €7m were awarded to Fluor as part of direct costs caused by the breach and included costs of additional project management staff, consultants’ costs for the remedial works and costs for extra plant and equipment, as well as for providing extra storage space.
However, in addition, Fluor also claimed for ‘thickening’ costs amounting to 4% of the award – comprising overheads to reflect the increased head-office costs that were necessitated as a result of dealing with the breach of contract. Fluor argued that the thickening costs were just as much a result of the breach as were the direct costs.
The landmark case introduced the concept that certain overhead costs can be linked to a breach of duty just as if they were ordinary losses, i.e. direct losses that include items such as new materials, extra labour and consultant costs necessitated by the breach.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Adversarial behaviour in the UK construction industry.
- Alternative dispute resolution.
- Arbitration.
- Causes of construction disputes.
- Civil procedure rules.
- Conflict avoidance.
- Contract sum.
- Contractual right.
- Construction contract.
- Dispute resolution.
- Dispute resolution boards.
- Disruption claims in construction.
- Expert witness.
- Extension of time.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- How to prepare a claim for an extension of time.
- Litigation.
- Liquidated damages.
- Loss and expense.
- Mediation.
- Modifying clauses in standard forms of contract.
- Notice.
- Preliminaries.
- Scheme for Construction Contracts.
- Variation.
- What is a default?
Featured articles and news
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.





















