Types of costs for buildings
Contents |
[edit] Introduction
The idea of ‘cost’ in relation to buildings is not a simple one, as there are a wide range of different types of cost. This article provides a brief summary of those types, with links to sources of additional information.
[edit] Capital cost
Capital costs are those costs associated with one-off expenditure on the acquisition, construction or enhancement of significant fixed assets including land, buildings and equipment that will be of use or benefit for more than one financial year.
[edit] Construction costs
Construction costs are those costs incurred by the actual construction works themselves, and on some projects may be determined by the value of the contract with the main contractor.
For more information see: Capital costs.
[edit] Building operating costs
Building operating costs are the costs incurred gy the day-to-day operation of the building, which might include; utilities costs, maintenance and repairs, general and administrative expenses and so on.
[edit] Business operating costs
Business operating costs may include building operating costs and also other operating costs such as; rent, wages and so on.
[edit] Life cycle costs
Life cycle costing is an economic assessment of the discounted net present value of life cycle costs, carried out using profiles of current and future costs and benefits. There is increasing emphasis on life cycle costing to ensure all costs are taken into account during the decision-making process, not just those for capital investment.
For more information see: Life cycle costing.
[edit] Whole life costs
Whole life cost. Whole-life costs consider all costs associated with the life of a building, from inception to construction, occupation and operation and disposal.
For more information see: Whole life costs.
[edit] Out-turn costs
Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
For more information see: Out-turn cost.
[edit] Other types of costs
Other types of cost might include:
- Abnormal cost.
- Base cost.
- Baseline costs.
- Cost in use.
- Defined cost.
- Direct cost.
- Disallowed cost.
- Environmental cost.
- Outturn cost.
- Prime cost.
- Project cost.
- Provisional cost.
- Real cost.
- Replacement cost.
- Relevant cost.
- Renewal cost.
- Social cost.
- Sunk cost.
- Target cost.
- Tender cost.
- Total cost.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.


















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.