Substructure
The Building Cost Information Service (BCIS), Elemental Standard Form of Cost Analysis Principles, Instructions, Elements and Definitions 4th (NRM) Edition published by the Royal Institution of Chartered Surveyors (RICS) in 2012, describes the rules for preparing an elemental cost analysis in standard BCIS format.
It defines the term substructure as:
‘All work below underside of screed or, where no screed exists, to underside of lowest floor finishes including damp-proof membrane, together with relevant excavations and foundations (includes walls to basements designed as retaining walls).’
It suggests that the function of the substructure is to, ‘… transfer the load of the building to the ground and to isolate it horizontally from the ground.’
According to BCIS, the substructure includes:
- Foundations up to and including the damp proof course.
- Lowest floor assembly below the underside of the screed or the lowest floor finish.
- Basement excavation.
- Basement retaining walls up to and including the damp proof course.
This a fairly narrower definition which excludes items such as; finishes, basement walls not in contact with earthwork, retaining walls not providing external walls, and so on.
Some much broader definitions consider the substructure to include all works below ground level, although clearly, this is a fairly ambiguous description.
[edit] Related articles on Designing Buildings Wiki
- Basement.
- Basement excavation.
- Basement v cellar.
- Building Cost Information Service.
- BCIS elements.
- Concept structural design.
- Cost planning.
- Deflection.
- Diaphragm wall.
- Elemental cost plan.
- Excavation.
- Footings.
- Groundworks.
- Planning (Subterranean Development) Bill.
- Structure definition.
- Structural engineer.
- Structural principles.
- Substrate.
- Superstructure.
- Types of structure.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.