Soil vent pipe
A soil vent pipe (SVP), also known as a soil stack pipe, drain-waste-vent or ventilated discharge pipe, is typically a vertical pipe that removes sewage and greywater from a building. It is often attached to the exterior of a building (although it may be fitted internally) and connects the subterranean drainage system to a point just above the level of the roof gutter.
Soil vent pipes allow the removal of waste from toilets, showers, baths and sinks, while also allowing odours to be released above the building, via a stack vent, at a level that will not cause a nuisance. The pipe’s vents also allow air into the internal drainage system so as to facilitate the process of aerobic sewage digestion, preventing a siphoning affect from occurring, and allowing free flow by gravity.
SVPs must maintain sufficient downward slope along their length to keep liquids and entrained solids flowing freely towards the drain. If a downward slope is not possible, a collection pit with a ‘sewage ejector’ pump can be installed.
Traditionally, soil vent pipes were made from cast iron; however, today they are most commonly made from uPVC.
Approved document H: Drainage and waste disposal requires that the foot of a discharge stack should have as large a radius as possible, and not less than 200 mm at the centre line. Offsets should be avoided in the wet section of the stack. Ventilating pipes should finish at least 900 mm above any opening within 3 m and should be finished with a wire cage or other perforated cover.
[edit] Related articles on Designing Buildings
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.