Self-build home: Prepare production information
Introduction.
In this stage, we attribute design activities to ‘designers’. These may be architects and engineers, a design and build contractor, or a kit house supplier. If a kit house supplier is only supplying the house itself, additional design consultants may be required.
Production information is '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed'.
The designer should develop a schedule of production information, responsibilities for its preparation, a programme for its preparation and a document control system for version control.
Production information may include:
- Drawings (location drawings, component drawings and dimensioned diagrams).
- Specifications, calculations and design criteria. Specifications provide descriptions of the materials and workmanship required. Design criteria might include; environmental conditions, acoustic requirements, critical dimensions, accessibility requirements, loadings and so on.
- Bills of quantities or schedules of work. Bills of quantities are measured quantities of the work identified on the drawings and specifications that can be used to cost the works. Schedules of work are 'without quantities' instructional specifications often produced on smaller projects, or for items such as builders work or fixing schedules.
There should be a particular emphasis on equipment with long lead time times that could delay the project, such as:
- Bespoke cladding systems.
- Service diversions.
- Demolition.
- Underground drainage.
- Piling and groundworks.
Preliminary contracts might be considered for some of these works to allow them to begin early. Long-lead items such as piling rigs might also be ordered in advance of other works.
The quality of production information is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred.
Many elements of production information will be produced by suppliers or contractors. The designer should check drawings and specifications provided by suppliers and contractors to ensure they are properly co-ordinated.
Increasingly, software is used to prepare elements of production information, such as; computer aided design (CAD) to prepare drawings, and proprietary systems for the preparation of specifications. The recent emergence of building information modelling (BIM) can allow the automatic generation of production information from a single co-ordinated model, which should result in a reduction in errors and so costs.
NB During this stage, the lead designer should also co-ordinate any outstanding information needed for remaining building regulations or other statutory approvals which must be submitted before works start on site. It is also important to ensure that any necessary party wall notices have been served.
Next stage:
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.





















