Self-build home: Confirm appointment of the design and build contractor to construct the home
NB Where a single-stage procurement route has been followed, and the contractor’s initial appointment was for both design and construction, the contract sum for the construction of the home will already have been agreed.
Ideally, when the the design and build contractor's appointment to construct the home is confirmed, negotiation is a mathematical exercise following the pricing criteria agreed in the first-stage when the contractor was appointed to design the home.
The first-stage appointment might have been made on the basis of a bespoke agreement, a consultancy agreement or a pre-construction services agreement (PCSA), with an appendix setting out the tender items to be applied to the construction contract, with a clause that made it clear there is no obligation to proceed to the construction contract, and in such circumstances the pre-construction fee would be full and final settlement of the contractor's costs.
However, there are likely to be items not anticipated in the first stage, for which negotiations will be necessary.
Negotiating at this point is difficult because the contractor is ‘embedded’ in the project and there is little threat from competition. This can mean that tender prices for the second stage of two-stage contracts are higher than traditional contracts, which are subject to full competition. However, there tend to be fewer variations and fewer claims; as the contractor has a longer period of familiarity with the project and a better-developed relationship with the self builder.
Ideally there will be some means of securing an alternative bid if negotiations with the contractor fail, albeit this is likely to result in delays and difficulties in attributing design liability.
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.