Pre-tender estimate for contracts
The pre-tender estimate (PTE) is the final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers. The pre-tender estimate itself is not included in the tender documents.
It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders.
It also gives a basis for assessing and comparing tenders when they are returned.
If the pre-tender estimate exceeds the approved budget, an explanation should be provided for the client to consider and issue instructions.
As with the tender documents, the pre-tender estimate should be broken down into a series of packages (even if there will only be one main contract), this will allow easy appraisal of tenders received, which are likely to prepared by contractors based on prices of packages received from sub-contractors. It ensures that the tenders are easily compared with one another and with the pre-tender estimate, and any anomalies or potential savings identified.
The pre-tender estimate should be prepared following a standard approach to estimating such as that defined by the new rules of measurement (NRM).
NB: A post tender estimate is '…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project.' For more information, see Post tender estimate.
[edit] Related articles on Designing Buildings
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Cash flow projection.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Estimator.
- Final account.
- Front-loaded costs.
- Initial cost appraisal.
- New Rules of Measurement.
- Order of cost estimate.
- Post tender estimate.
- Tender pricing document.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 2 June
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.


















Comments
what is cost reconciliation and why is there one on all submitted tenders is required before placing a contract.