OGC gateway review 0
The Office of Government Commerce (OGC) has now been absorbed into the Efficiency and Reform Group (ERG) within the Cabinet Office.
When it existed, the OGC produced a great deal of guidance about best practice in procurement and project management. This OGC guidance has now been archived, however, it is still cited in the new Government Construction Strategy and the revised Common Minimum Standards (to become the 'Construction Standards') and links are still provided from government websites such as the Major Projects Authority. The OGC gateway review process still provides one of the best and most comprehensive sets of guidance for public projects. It is for this reason that the project plan for public projects within Designing Buildings Wiki follows the OGC gateway review process. See Public project: outline work plan.
The procurement routes preferred by the Government Construction Strategy and described by the OGC gateway review process are private finance initiative (PFI), prime contracting and design and build (see OGC Achieving Excellence Guide 6:Procurement and contract strategies). The Government Construction Strategy states that traditional procurement routes that separate design from construction should not be used unless it can be demonstrated that they offer better value for money.
The three preferred routes involve appointing a single integrated supply team (including designers, contractors, suppliers and perhaps facilities managers) after the project brief has been prepared, before design commences. This means that the main decision to invest (i.e. to appoint the integrated supply team), takes place before any designs have been prepared.
The OGC Gateway Review process offers a structure for projects following these procurement routes, based around a series of independent peer reviews carried out at key stages to verify that projects should be allowed to progress to the next stage.
These peer reviews, or 'gateway reviews' are commissioned on a confidential basis by the Senior Responsible Owner:
- OGC gateway review 0: strategic assessment.
- OGC gateway review 1: business justification
- OGC gateway review 2: delivery strategy (or procurement strategy)
- OGC gateway review 3: investment decision
- OGC gateway review 4: readiness for service
- OGC gateway review 5: operations review & benefits realisation (or benefits evaluation)
There are also two additional decision points specific to building projects:
In practice, some of the design work leading up to these decision points is likely to be carried out during the tender process (or bidding process on PFI projects).
Gateway review 0: strategic assessment is the first gateway. It is a programme review that takes place before it has been decided to proceed with a project, it
... investigates the direction and planned outcomes of the programme.... It makes a strategic assessment of the proposed project, its contribution to the business strategy, drivers and benefits and considers the high level options.
ref OGC introduction to procurement gateway 0
The review ensures:
- the scope and purpose of the programme has been adequately researched
- that there is a shared understanding of what is to be achieved by the key stakeholders
- that it fits within the organisation’s overall policy or management strategy and priorities
- that there is a realistic possibility of securing the resources needed for delivery
- that any procurement takes account of prevailing government policies
- the work strands will be organised (in sub-programmes, projects, etc) to deliver the overall programme objectives, and that the programme management structure, monitoring and resourcing is appropriate
ref OGC gateway process review 0: strategic assessment.
According to OGC the tasks specific to construction projects that should be undertaken before OGC Gateway Review 0: Strategic assessment are:
- Possible need for project brought to attention of the investment decision maker (IDM) – the role responsible for making investment decisions on behalf of the business; typically the management board or similar senior group.
- A senior manager in the business unit that requires the project, appointed by and reporting to IDM. The senior responsible owner (SRO) owns the project and is personally accountable for its success
- The project sponsor (PS) should have an understanding of the culture business of the client department. SRO to provide terms of appointment for PS (project sponsor).
- Experts in the relevant subject (for example, business strategy, legal, financial, construction, design, etc) to advise on options to meet the business need, including whether a construction solution will best meet the client’s needs.
- The PS, in consultation with the SRO, should identify the stakeholders for the project. Stakeholders may be internal (eg Heads of Division, users etc) or external (eg members of the public as customers, pupils, patients).
- Carry out a value management (VM) study to identify business/stakeholder needs, both short and long term. Set objectives, including Health & Safety, sustainability and design quality (using Design Quality Indicators – DQIs), agree priority and agree on performance indicators to show that these are being met. Note that the success of the project will be measured against objectives/KPIs.
- Explore high level options for meeting the business need and assess in principle their affordability and achievability. Identify time related factors – that is, an optimum timespan for the life of the facility. Be prepared to revisit initial thinking on high level options, to ensure that all appropriate opportunities are given full consideration.
- Carry out high level risk assessment and capture in a risk register; include the risk of the optimum timespan being incorrect.
- Research previous similar projects and identify appropriate lessons to apply to the project.
- Prepare project brief and outline PEP to inform strategy and control of project, including roles and responsibilities. (Note that responsibility for maintaining the PEP passes to the project manager when appointed.)
- Establish strategic fit of project with key business objectives.
- Approval to proceed.
ref Achieving Excellence Guide 3 - Project Procurement Lifecycle P9 and 10.
It can be appropriate to carry out more than one gateway 0 reviews.
For a detailed description of the sequence of tasks necessary on public projects, see the free work plan available from Designing Buildings Wiki: Public project: outline work plan. Gateway review 0 takes place during the work stage: Public project: business justification.
[edit] Related articles on Designing Buildings Wiki
- Change control.
- Design and build.
- Designing Buildings Wiki: Public project: outline work plan.
- Gateways.
- Government Construction Strategy.
- OGC.
- Output based specification.
- Private Finance Initiative.
- Prime contract.
- Public procurement.
- Public project: business justification.
- Major Projects Authority.
[edit] External references
Featured articles and news
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.