Non-negligent liability insurance
Construction is an inherently dangerous process with many hazards, in particular when working close to existing buildings or other structures. In such situations, there is the potential for that property to suffer damage, even if care is exercised.
As a result of the potential for these sorts of losses to occur on construction projects, Joint Contracts Tribunal (JCT) contract forms provide for non-negligent liability insurance to be taken out, and other forms of contract may have similar provisions, either as part of the standard form or as an amendment.
Such provisions require that the contractor takes out a policy that protects the developer in respect of any expense, liability, loss, claim or proceedings incurred as a result of damage to property from the works being undertaken due to; collapse, subsidence, heave, vibration, weakening or removal of support and lowering of ground water. It is also possible to include cover from the hazards of flood, explosion, backing up of drains and bodily injury to third parties caused by an insured peril.
The cover may be in respect of existing buildings being worked upon and/or property on adjoining land. The policy is issued in the joint names of the employer and contractor.
This sort of cover is not always be required as the kind of activities which give rise to such losses may not be present on all projects. Consultants will usually be able to recommend whether or not the cover is required.
There are a variety of activities that could give rise to the potential hazards covered by the insurance, including:
- Piling and foundation excavations
- Underpining.
- De-watering of the ground
- Demolition close to an existing property.
- Shoring of walls
- Works that may affect the load-bearing capacity of a structure.
- Works on listed buildings or buildings in a poor condition.
Typical exclusions from non-negligent cover might include:
- Damage caused by negligence, omission or by default of the contractor or subcontractor.
- Damage which is due to error or omissions during the design process.
- Damage which could reasonably have been foreseen as inevitable.
- Penalties incurred under contract and damages for breach of contract.
The Royal Institute for Chartered Surveyors (RICS) have produced a guidance note which provides further information on non-negligent liability insurance, including details of Gold v Patman & Fotheringham (1958), the landmark case in this situation.
[edit] Related articles on Designing Buildings Wiki.
- 3D animation for insurance risk analysis.
- Building Users' Insurance Against Latent Defects.
- Contractors' all-risk insurance.
- Contract works insurance.
- Directors and officers insurance.
- Employer's liability insurance.
- Flood insurance.
- Insurance.
- Insurance terminology.
- Integrated project insurance.
- Latent defects insurance.
- Legal indemnity insurance.
- Professional Indemnity Insurance.
- Public liability insurance.
- Residual value insurance.
[edit] External references
Featured articles and news
Extended reality in a post-pandemic world.
Can XR technology be leveraged in design & construction?
Or are you capping.
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.