Cost reimbursable contract
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee. Option E of the NEC3 Engineering and Construction Contract (ECC) is an example of a cost reimbursable contract.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business). Tendering may proceed based on an outline specification, any drawings and an estimate of costs.
This is a high risk form of contracting for the client as the final cost is not known when the contract is entered into (i.e. there is no contract sum).
The costs for which the contractor is entitled to be reimbursed must be set out very clearly in the contract. This is a complex procedure that needs to be carefully considered, as whilst some direct costs may be relatively straight forward to determine, whilst other ‘shared’ costs, might not.
Direct costs that are clearly attributable to a single project could include:
- Labour.
- Materials.
- Hired plant.
- Sub-contractors.
Other costs that might be spread across more than one project could include:
- Head office costs.
- Staff costs.
- Manufacturing facilities.
- Owned plant.
These costs might be calculated on a pro-rata basis and charged, along with profits as a pre-agreed lump sum, or percentage fee.
In order that the contractor can maintain their cash flow, cost reimbursable contracts may also allow them to charge for liabilities, or for costs that will be incurred before the next interim payment.
Costs are calculated based on the contractor’s accounts and other records, which are made available to the client on an ‘open book’ basis. The client may also monitor activities on site to verify that costs are legitimate (for example, checking whether plant that is being charged is actually being used) and that costs are not excessive. This can become complex where the contractor is thought to be operating inefficiently or incompetently.
The contractor can be incentivised to operate efficiently by the introduction of a target cost. Here, a target cost is agreed at the beginning of the project. At the end of the project the actual cost is compared to the target cost (taking into account any changes that have been agreed). If the actual cost is lower than the target cost, the savings are shared between the parties to the contract on some pre-agreed basis (often a percentage). If the actual cost is higher than the target cost, the additional costs may also be shared.
NB: JCT suggest that a prime cost contract, cost plus and cost reimbursable contract are in fact the same thing. Others consider that a prime cost contract is one in which the cost of works packages (the prime cost) are reimbursed, but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
There are three types of cost reimbursable methods used in the construction industry.
- Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
- Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
- Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Related articles on Designing Buildings
- Admeasurement.
- Contractor.
- Construction contract.
- Contract conditions.
- Contract sum.
- Defined cost.
- Disallowed cost.
- Interim certificate.
- Key dates.
- NEC Option E: Cost reimbursable contract.
- NEC3.
- Open-book accounting.
- Prime cost contract.
- Procurement route.
- Remeasurement.
- Specification.
- Sub-contractors.
- Target cost.
- Tender.
- Time and material contract (T&M).
[edit] External references
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.