Construction progress report
Construction progress reports are prepared regularly (often monthly) by the contract administrator during the construction phase and issued to the client. They will generally be a summary of the reports received and discussions held at construction progress meetings.
Construction progress reports may be a combination of minutes of construction progress meetings and reports received during those meetings, with key issues highlighted in an accompanying cover note. Alternatively they may be a re-written version of that information prepared specifically to suit the client's requirements.
Construction progress reports might include:
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Weather reports.
- An assessment of any health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
Similar reports may be prepared on management contract projects in relation to works contractor progress.
[edit] Related articles on Designing Buildings Wiki
- Client.
- Construction progress meeting.
- Construction manager.
- Contractor.
- Contract administrator.
- Consultant team.
- Construction stage report.
- Earned value analysis.
- Employer's agent.
- Health and Safety.
- Management contractor.
- Progress of construction works.
- Project programme.
- Project manager.
- Project manager's report.
- Site meeting.
- Sub contractor.
- Warranties.
- Works contractor
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.


















Comments