Construction progress report
Construction progress reports are prepared regularly (often monthly) by the contract administrator during the construction phase and issued to the client. They will generally be a summary of the reports received and discussions held at construction progress meetings.
Construction progress reports may be a combination of minutes of construction progress meetings and reports received during those meetings, with key issues highlighted in an accompanying cover note. Alternatively they may be a re-written version of that information prepared specifically to suit the client's requirements.
Construction progress reports might include:
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Weather reports.
- An assessment of any health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
Similar reports may be prepared on management contract projects in relation to works contractor progress.
[edit] Related articles on Designing Buildings Wiki
- Client.
- Construction progress meeting.
- Construction manager.
- Contractor.
- Contract administrator.
- Consultant team.
- Construction stage report.
- Earned value analysis.
- Employer's agent.
- Health and Safety.
- Management contractor.
- Progress of construction works.
- Project programme.
- Project manager.
- Project manager's report.
- Site meeting.
- Sub contractor.
- Warranties.
- Works contractor
Featured articles and news
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
Comments