Bid evaluation
![]() |
This article should be read alongside Tender evaluation.
A tender, or 'bid' is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods and/or services.
Bid evaluation is the process that takes place after the tender submission deadline. It involves the opening and examining of the bids to identify the preferred supplier(s) for the project. Negotiations may then be entered into with one or more suppliers, and the successful supplier awarded the contract.
NB: There may have been a pre-qualification process before bids were invited to reduce the number of potential tenders to those that are genuinely appropriate for the project,
Generally, bid evaluation will be carried out in accordance with evaluation criteria or a selection methodology specified in the invitation to tender. Criteria or other factors that were not included in the invitation to tender should not be used to evaluate bids, and ideally, the same evaluators should evaluate all bids.
Bidding parties should submit clear and well-organised bids, but nonetheless, a great deal of thoroughness is required in the bid evaluation process, to ensure that proposals are properly understood, bids are compliant with invitation to tender, no information is overlooked and that correct conclusions are reached.
An initial review of the offers received is generally undertaken to determine their responsiveness and conformity to the conditions in the invitation to tender documents. Non-compliant bids may be rejected (unless a compliant bid has also been submitted).
A more detailed evaluation of compliant bids may then be undertaken against a number of pass/fail criteria. A technical determination should be made to ascertain whether the bidder’s technical solution is feasible, appropriate and deliverable within certain requirements, i.e. safety and costs. If a consortium has submitted the bid, the proposed project management should be assessed to determine how cohesive it will be in terms of delivering the project.
See Tender evaluation for more information.
There are a number of criteria upon which a preferred bidder can be identified:
- Lowest price
- Most economically advantageous tender (MEAT)
- Mean value
- Exclusion of the extremes
See Contract award for more information.
While it is common for the lowest priced tender to be awarded the contract, other factors – such as relevant experience and the perceived quality of the solution – should also be taken into consideration, as the lowest price does not always result in the best long-term value.
It may be the case that after the initial review only one bid will be sufficiently compliant. The lack of compliance or lack of interest may be because of deficiencies in the tender documents. If this is the case, then the tender documents could be rectified and the tender procedure begun again.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Best value procurement.
- Bidder.
- Bid writer.
- Competitive tender.
- Construction contract.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Selection criteria.
- The benefits of e-procurement in construction.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Comments
https://autocadfiles.com/amp/residential-house-apartment-design-in-autocad-file-download
Residential House apartment design in autocad file</a> Download file, Bed Room & other room architecture Furniture detail & all interior design, PArking lay-out & Side section & Stair detail.