Liquidation in the construction industry
Contents |
[edit] Introduction
The term ‘insolvency' describes the inability of a debtor to pay its debts. In the United Kingdom, insolvent individuals are made 'bankrupt', while companies are put into 'liquidation' or 'administration'. In cases of administration, a key objective is to try to ensure the company survives, whereas in liquidation, the company will generally not survive.
Insolvency proceedings are administrative processes instigated by either the insolvent entity or one of their creditors to recover assets so for disposal, the proceeds of which are distributed to creditors.
The Insolvency Act 1986 sets out four types of procedures governing the affairs of insolvent companies:
- Company Voluntary Arrangements.
- Administration.
- Receivership (less common following the enactment of the Enterprise Act 2000).
- Winding up leading to liquidation.
[edit] Liquidation
A company may be wound up either by court order or voluntarily. A court may wind up a company on presentation of a petition on grounds such as being unable to pay its debts.
A company can be deemed unable to pay its debts for a number of reasons, including:
- A statutory demand for a debt being served on the company and the company failing to satisfy that debt within three weeks.
- A court judgment against it, where steps to enforce the judgment have been unsuccessful.
- It is proved that the company is unable to pay its debts.
- Its assets are less than its liabilities.
Where a winding up order is made, this has the effect of discharging all employees, ending any agency relationships, and dismissing the company’s directors.
A liquidator is appointed to dispose of the company’s assets to discharge its liabilities to creditors, with any surplus being passed to whomever is entitled to it. Liquidators hold wide powers, constituting the governing body of the company and the receiver of its assets. They are entitled to their own costs before proceeds are distributed to creditors.
Once the process is complete the company is dissolved, which means that it has ceased to exist.
[edit] Liquidation of the main contractor
Liquidation is less common that administration in the construction industry. In the case of Carillion in 2018, it is thought that liquidation was chosen as there were insufficient remaining funds to appoint an administrator. Contractually, the consequences are the same, treated simply as 'insolvency'.
Insolvency of contractors is relatively common due to the low margins that they typically operate with, the high risk of project costs increasing, and constant cash flow and late payment issues.
Signs that a contractor may be in difficulties can include:
- Inactivity, or a lack of materials or plant on site.
- Late payments.
- An increase in the number of disputes, claims and exaggerated claims.
- Requests for advance payment.
- Lack of response to communications.
Most contracts will allow employers to terminate the employment of the contractor in the event of contractor insolvency and to cease payment. Typically, the contract will also allow them to employ others to complete the works and to use plant, tools, equipment, materials, temporary buildings and so on to do so. However, the employer must be certain of the insolvency first, and may seek evidence to confirm the fact.
This still leaves the employer having to find a new contractor and this can be time consuming and expensive, with other prospective contractors knowing that the employer is in a weak negotiating position. They client may also need consent from funding bodies to replace the contractor.
There may also be issues about:
- The ownership of goods, materials and so on that the employer has paid for, but are not in possession of.
- Goods or materials that have been delivered to site but not fixed to the building or paid for (which suppliers may attempt to remove).
- Defects in the works that the contractor has not rectified.
- Latent defects that may not yet be apparent.
- Outstanding payments.
- Overpayment for work that has not been completed.
- Advance payments.
- Outstanding disputes.
The situation is complicated by the prevalence of sub-contracting in the industry. The employer's main contractual link to subcontractors is through the contractor, and this link is been broken by the insolvency. The employer may be protected to some extent by provisions such as collateral warranties and step in rights.
However, the complexity and extent of the supply chain means that the knock on effects of main contractor insolvency can be far reaching. This is exacerbated by the fact that late payment is rife, and so companies in the supply chain of the insolvent company might be owed very large sums of money that they may be unable to continue without.
Other provisions that might give the employer some protection from main contractor insolvency include:
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Carillion.
- Collateral warranties.
- Government procurement post-Carillion.
- Insolvency.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Parent company guarantees.
- Performance bonds.
- Project bank accounts.
- Retention of title.
- Retention.
- Step in rights.
- Vesting certificate.
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.