In the UK construction industry, "Anticipated Final Account" (often referred to simply as "Anticipated Final") refers to the projected final cost of a construction project. This figure includes all expected expenses up to the completion of the project, considering any known changes, variations, and adjustments that might occur during the construction process. It is is a dynamic and continuously updated estimate of the total expected cost of a construction project. It plays a crucial role in budget management, cost control, and financial planning, helping ensure the project is completed within the anticipated financial parameters.
- It helps project managers and stakeholders keep track of the overall budget. By continually updating this figure, they can anticipate potential cost overruns and take corrective measures to manage the project within the approved budget.
- It accounts for all variations and changes to the original contract scope. This includes any additional work requested by the client, unforeseen circumstances, or necessary adjustments to the project plan.
- It serves as a tool for cost control, allowing stakeholders to compare the current anticipated costs with the original budget or contract sum. Any significant deviations can trigger discussions on cost-saving measures or the need for additional funding.
- It is used for financial forecasting and reporting. It provides a realistic picture of the project's financial status, which is essential for cash flow management and financial planning.
- By regularly updating the Anticipated Final, project managers can monitor the financial progress of the project. This helps in identifying and addressing any cost-related issues early on.
- It is a vital communication tool for keeping clients informed about the financial status of the project. Regular updates on the Anticipated Final help manage client expectations and ensure transparency.
[edit] Related articles on Designing Buildings
- Accounting.
- Campaign for cash retentions reform.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plans.
- Cost reporting.
- Cost value reconciliation.
- Defects.
- Final account.
- Final certificate.
- Fluctuations.
- Housing Grants, Construction and Regeneration Act.
- Liquidated damages.
- Loss and expense.
- New Rules of Measurement.
- Outturn cost.
- Pre-tender estimate.
- Prime cost sums.
- Provisional sums.
- Retention bond.
- Scott schedule.
- Tender pricing document
- Variations.
- Whole-life costs.
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.