Planning enforcement powers
Planning permission is the legal process followed in order to decide whether proposed developments should be allowed to go ahead. Responsibility for planning permissions lies with local planning authorities (usually, the planning department of the district or borough council).
Other than permitted developments, (which are considered to have insignificant impact), all developments require planning permission.
Permissions may be the subject of planning conditions, where, rather than refusing a planning application, a local planning authority might grant permission, but might for example restrict the use of the site or, require additional approvals for specific aspects of the development.
Planning enforcement is the process of investigating and resolving possible breaches of planning law. Breaches might include:
- Not obtaining planning permission for works that require permission (including; listed buildings, satellite dishes, advertisements, protected trees and so on).
- Not carrying out works in accordance with a permission.
- Not complying with planning conditions or other limitations.
- Changing the use of a site or buildings without obtaining planning permission where planning permission is required.
Local planning authorities have discretionary power to investigate and enforce these breaches using whatever enforcement action may be necessary in the public interest.
The National Planning Policy Framework (NPPF) states ‘...local planning authorities should act proportionately in responding to suspected breaches of planning control. Local planning authorities should consider publishing a local enforcement plan to manage enforcement proactively in a way that is appropriate to their area. This should set out how they will monitor the implementation of planning permissions, investigate alleged cases of unauthorised development and take action where it is appropriate to do so.’
The Town and Country Planning Act 1990 sets time limits for enforcement, after which developments are immune from action. In most cases, these are:
- Within four years of substantial completion for a breach of planning control consisting of operational development.
- Within four years for an unauthorised change of use to a single dwellinghouse.
- Within ten years for any other breach of planning control (changes of use).
Possible enforcement actions include:
- No formal action.
- Retrospective planning application.
- Planning contravention notice (to require information or seek suggestions for how to remedy the breach).
- Enforcement Notice (giving notice of what the breach is and setting out the steps the local authority require to remedy the breach).
- Planning Enforcement Order (when a person has deliberately concealed unauthorised development, a planning enforcement order enables action to be taken notwithstanding the fact that the time limit may have expired).
- Stop Notice (prohibiting activities in a related enforcement notice).
- Temporary Stop Notice (requiring that an activity which is a breach of planning control should stop immediately).
- Breach of Condition Notice.
- Injunction.
For more information see Planning Practice Guidance, Planning enforcement – overview.
It is illegal to disobey an enforcement notice (unless it is successfully appealed) and failure to comply can result in prosecution.
Building owners may appeal to the Planning Inspectorate against an enforcement notice on specific grounds as long as the appeal is received by the Planning Inspectorate before the ‘effective date’ on the notice. See Planning Portal Enforcement appeals for more information.
However, it is important to note that enforcement action is discretionary and so it may be more productive to seek early engagement with the local authority and to attempt to negotiate an agreement before an enforcement notice is served, rather than appealing.
[edit] Related articles on Designing Buildings
- Avoiding planning permission pitfalls.
- Development management.
- Enforcement activity.
- Enforcement notice.
- How long does it take to get planning permission.
- How long does planning permission last.
- Listed buildings.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning obligations.
- Planning permission.
- Retrospective planning application.
- Stop notice.
- Temporary stop notice.
[edit] External references
Featured articles and news
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.























Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.