The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘tender works programme’, refers to:
|
A programme based on a global strategy for the project resulting from the information available at tender stage. It should not be relied on for construction purposes but may legitimately be the basis for the construction master programme. Its purpose is to demonstrate that the contractor intends to comply with the date constraints listed in the tender documents and, where a contract period is not specified, it will indicate the completion date and hence, the duration over which the time-related site costs must be included in the tender. It should be prepared as a critical path network in order to identify critical work activities and delivery dates of client supplied information, goods and materials. It is not uncommon for the tender documents to require the tender works programme to be submitted with the tender. |
NB, This should not be confused with the 'tender preparation programme', which is the, ‘…resourced activity schedule outlining (the) programme for the preparation and submission of (the) tender’.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Chartered Institute of Building.
- Code of Estimating Practice.
- Contract documents.
- Contractor's master programme.
- Cost plans for construction projects.
- Design programme.
- Information release schedule.
- Milestones.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Short period programme.
- Tender documents.
- Tender.
- Time-location chart.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.