Cost plans for construction projects
Contents |
[edit] What are cost plans?
Cost plans are generally prepared by cost consultants (often quantity surveyors), and provide a snapshot of the likely costs associated with construction works. They evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the design, and then actual prices are provided by suppliers.
[edit] What are the different types of cost plan?
Starting with initial appraisals at the beginning of a project and evolving through to the final account, the range of types of cost plan that might be prepared on a project include:
- Initial cost appraisal (studies of options prepared during the feasibility study stage).
- Elemental cost plan (prepared during the project brief stage and carried through to detailed design).
- Approximate quantities cost plan (from the end of detailed design through to tender).
- Pre-tender estimate (prepared alongside tender documentation).
- Tender pricing document (strictly speaking this is not a priced document, but is part of the tender documentation issued to the contractor for pricing).
- Contract sum (agreed with the contractor during the tender period and adjusted during the construction period).
- Contract sum analysis (a break down of the contract sum prepared by the contractor on design and build projects).
- Final account (agreed during the defects liability period).
[edit] What is included in cost plans?
Other than initial cost appraisals, these all relate to the construction cost of the project (rather than wider project costs that the client might incur, which could include; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on). It is important that the client makes clear what costs should be included in cost plans and what will remain within the control of the client organisation.
Initial cost appraisals are carried out without the benefit of a design for the project. They include client costs that may not feature in later cost plans and as a result will almost certainly need input from the client's finance director or financial advisers.
Once the initial cost appraisal is completed, the client will decide the scope of costs that will in future be monitored by the cost consultant and those that will be monitored and controlled by the client organisation.
[edit] Sources of other information about cost plans
Articles about cost plans and cost control on Designing Buildings include:
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Cash flow.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost control.
- Cost engineering.
- Cost monitoring.
- Cost of building.
- Cross estimating method.
- Elemental cost plan.
- Estimate.
- Final account.
- Initial cost appraisal.
- Measurement.
- New Rules of Measurement.
- Order of cost estimate.
- Outturn cost.
- Pre-tender estimate.
- Stage 2 cost plan.
- Stage 3 cost plan.
- Tender cost.
- Tender pricing document.
- Whole-life costs.
Featured articles and news
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.























Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.