Profit and overheads on construction projects
Contents |
[edit] What are profit and overheads?
On construction projects, profit and overheads are normally referred to in relation to contractors.
In terms of individual projects, profit can be defined as the money the contractor makes after accounting for all costs and expenses. The percentage profit a contractor might apply to their tender price will vary according to risk, workload and economic climate. It can also relate to the turnover of capital employed for each project; the more times a contractor can turnover its capital on a project the more it can afford to cut margins.
For more information see: Profit.
Overheads are often priced proportionately against a project and are the calculated costs of running the company contracted to carry out a project. Often these costs are described as head office administrative costs (in some cases there may be factory or manufacturing overheads).
Head office or administrative costs might include; property costs, finance charges on loans, insurances, staff, taxes, external advisors, marketing and tendering activities. Most contracting organisations will calculate a percentage against project costs to be set against each project somewhere between 2.5% and 10% to cover head office services.
'Site overheads' such as site accommodation, insurance, and so on, do not fall within this definition of profit and overheads, but are included in the preliminaries element of the contract. For more information see: Preliminaries.
For more information see: Overheads
According to NRM1: Order of cost estimating and cost planning for capital building work, Main contractor’s overheads and profit, '...means the main contractor’s costs associated with head office administration proportioned to each building contract plus the main contractor’s return on capital investment. Main contractor’s preliminaries exclude costs associated with subcontractor’s overheads and profit, which are to be included in the unit rates applied to building works.'
[edit] Loss and expense
Construction contracts will generally provide for the contractor to claim direct loss and expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible (such as instructing variations to the works).
Very broadly, contracts generally allow direct losses to be recovered (such as the cost of labour and materials), but may exclude indirect or consequential losses (such as loss of profit). There is disparity between different contract types about whether head office overheads can be included in claims for loss and expense, as it is difficult to attribute them to a specific project.
For example, there is a grey area in relation to part-time project staff who are stationed at head office and may cover a number of projects. This can lead to double accounting. As a consequence it is best to agree the allocation of such staff costs before placing orders, and if there are specific losses which the parties to the contract wish to exclude, it may be wise to ensure that this is stated explicitly within the contract.
[edit] Prime cost contracts
On prime cost contracts the contractor is paid for carrying out the works based on the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. This fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
[edit] Related articles on Designing Buildings
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.