Nominated subcontractor v named subcontractor
Contents |
[edit] Introduction
Contractors may not have all the required skills or resources necessary to complete the works described in a construction contract, and so sub-contractors are commonly appointed to undertake those aspects of the project.
Typically, subcontractors are selected and appointed by the contractor themselves. These are referred to as ‘domestic’ subcontractors.
For more information see: Subcontractors.
[edit] Nominated subcontractors
Under certain circumstances, the client may wish to select (nominate) a subcontractor themselves, rather than allowing the contractor to select them. This is referred to as a nominated subcontractor.
This can happen; where the client has involved a subcontractor in the design process, where the client wishes to achieve a very specific outcome, where they have an existing relationship, or where the client needs to secure the supply of long lead-time items. Nominated subcontractors may be selected before or after the contract is entered into with the main contractor.
Ultimately, the nominated subcontractor is still appointed by the main contractor, but they are imposed on them by the client. This can be allowed for in the contract by a prime cost sum, to which the contractor is permitted to add profit and attendance.
Nominated subcontractors are less common in the UK than they used to be, and some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for the nomination of sub-contractors. This is because the contractual arrangements allowing nomination are very complicated, and as the main contractor has no choice in the selection of the nominated sub-contractor, the contract may, or may not hold them entirely responsible for failure of the nominated sub-contractor to perform (depending on the exact wording of the contract). The contractor will however generally be allowed the right to object to the subcontractor under certain conditions, and if the client still wishes to use the subcontractor, some contracts allow them to indemnify the main contractor against the possible consequences of this.
Because of these and other complexities, nomination is generally not used in UK contracts (such as JCT contracts), where the use of named sub-contractors is now generally considered to be a simpler alternative. However, some contracts still allow nomination, particularly international contracts such as FIDIC.
For more information see: Nominated subcontractor.
[edit] Named subcontractors
Naming subcontractors allows the client to influence the selection of sub-contractors whilst leaving responsibility for their performance with the main contractor.
The client names a short-list of subcontractors that would be acceptable to them in the tender documents for the main construction contract. The tender documents allow for this by including a provisional sum for the subcontract package. When tendering for the main contract, the main contractor makes allowances for mark up, attendance and programme in relation to the subcontract package.
Once appointed, the main contractor seeks tenders for the package from the named sub-contractors (although they may reasonably object to any of the named subcontractors). Once the main contractor has selected and appointed a subcontractor the provisional sum is replaced with the actual price agreed.
The main contractors assumes responsibility for the subcontractor’s performance. In effect the named sub-contractor becomes a domestic subcontractor, they are paid by the main contractor and the main contractor is responsible for their works.
For more information see: Named subcontractor.
[edit] Related articles on Designing Buildings
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.






















Comments
I thought nominated sub-contractor provision under JCT was removed in 2005 - Now we have listed (clause 3.8 in SBC) and named specialist (supplemental provision)