Negotiated Procedure without Prior Publication NPwPP
Contents |
[edit] Introduction
The Single Procurement Document (Scotland) - also referred to as SPD (Scotland) - is a document that contains questions used at the selection stage for post-Brexit procurement exercises in Scotland. It is used to identify suitably qualified and experienced bidders for public sector procurement in Scotland.
The Supplier Journey portion of the Scottish Government’s procurement guidance website offers an overview of the different types of procurement procedures that are available under SPD (Scotland). One such type of procurement is referred to as Negotiated Procedure without Prior Publication or NPwPP.
[edit] Definition
According to the STAR Procurement Glossary of Terms, a Negotiated Procedure without Prior Publication is: “A procurement procedure which can be used by public sector buyers to procure goods or services.”
The conditions under which this procurement route can be used in Scotland are narrowly defined and may be considered exceptional. These conditions may include:
- Where no tenders, no suitable tenders or no suitable requests to participate were submitted in response to an open or restricted procedure.
- Where, for technical or artistic reasons, or the protection or exclusive rights, the contract can only be carried out by a particular supplier. These reasons must be defined and justified.
- Due to extreme urgency as a result of unforeseen events e.g. flooding.
Under suitable circumstances, the procurement officer will approach one (or more) suppliers or service providers seeking to negotiate the terms of the contract.
NPwPP should be used under circumstances that have not been created by the organisation. Its use must be sufficiently justified, and examples as to why other options are not viable should be provided.
[edit] Related articles
- Competitive dialogue procedure for construction contracts.
- Competitive procedure with negotiation.
- Contract conditions.
- Negotiated contract.
- OJEU procurement procedures.
- Procurement route.
- Single Procurement Document (Scotland).
[edit] External resources
- Scottish Government, Procurement Journey, When to Use a Negotiated Procedure without Prior Publication.
- Scottish Government, Supplier Journey.
- STAR Procurement Glossary of Terms.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.