New Engineering Contract
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
The intentions of NEC contracts include:
- Stimulating good management.
- Being clear and simple, written in plain English, in the present tense and without legal terminology.
- Being useable in wide variety of situations from minor works to major projects
The suite of documents now include:
- NEC4: Alliance Contract
- NEC4: Design Build and Operate Contract
- NEC4: Dispute Resolution Service Contract
- NEC4: Engineering and Construction Contract
- NEC4: Engineering and Construction Short Contract
- NEC4: Engineering and Construction Short Subcontract
- NEC4: Facilities Management Contract
- NEC4: Facilities Management Short Contract
- NEC4: Facilities Management Short Subcontract
- NEC4: Facilities Management Subcontract
- NEC4: Framework Contract
- NEC4: Professional Service Contract
- NEC4: Professional Service Short Contract
- NEC4: Professional Service Subcontract
- NEC4: Supply Contract
- NEC4: Supply Short Contract
- NEC4: Term Service Contract
- NEC4: Term Service Short Contract
- NEC4: Term Service Subcontract
The Engineering and Construction Contract has 6 options:
- NEC4: Engineering and Construction Contract Option A priced contract with activity schedule
- NEC4: Engineering and Construction Contract Option B: priced contract with bill of quantities
- NEC4: Engineering and Construction Contract Option C: target contract with activity schedule
- NEC4: Engineering and Construction Contract Option D: target contract with bill of quantities
- NEC4: Engineering and Construction Contract Option E: cost reimbursable contract
- NEC4: Engineering and Construction Contract Option F: management contract
There are a number of articles relating to NEC on Designing Buildings:
- Accepted programme.
- Activity schedule
- Compensation event.
- Cost reimbursable contract.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early contractor involvement.
- Early warning notice.
- Key dates.
- Latham Report.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC contracts and collaborative working.
- NEC early contractor involvement.
- NEC early warning notices - a tool of mutual benefit.
- NEC3.
- NEC4.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- Period for reply.
- Term Contract.
- The NEC and the Z clause.
- Time Risk Allowance.
- Z clauses.
[edit] Related articles on Designing Buildings
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.