NEC early warning notices - a tool of mutual benefit
Rudi Klein, NEC Users’ Group President and Chief Executive at Specialist Engineering Contractors' (SEC) Group argues that the sooner we can appreciate that early warning notices are a tool of mutual benefit to both parties – and not designed to advantage one side over the other – the better.
Contents |
[edit] Introduction
I receive regular feedback from construction firms regarding the operation of NEC early warning notices. They normally comprise one or more of the following comments:
- "I always issue early warning notices, whatever the problem, to ensure I get a compensation event."
- "The other side issues early warning notices to establish it is my fault and I have to fix it immediately."
- "I am wary of issuing early warning notices because the other side uses them against me in the event of a dispute."
- "Everyone on the project ignores early warning notices."
It is clear that there are still some misconceptions about NEC early warning notices.
[edit] Risk management tool
Early warning notices have been a feature of NEC from the start – their inclusion separated NEC from the rest of the contractual pack.
They were introduced as a risk management tool because it is common sense that dealing with risk – wherever it comes from – as soon as it becomes apparent is far cheaper than trying to manage the risk and/or its consequences much later on.
Clause 16 of most NEC contracts makes clear the circumstances in which either party would be expected to issue an early warning notice.
An early warning notice must be issued as soon as a party becomes aware of 'any matter' which could affect the total of the prices, could delay completion or a key date, or impair the performance of the works in use.
Also, the contractor may give an early warning notice relating to any matter which could increase its total cost. Early warning matters should be entered on the risk register.
[edit] Mutual benefit to parties
Early warning notices should not be issued for the purpose of allocating responsibility or liability. A party attempting to do this could be failing to act in the NEC clause 10, 'spirit of mutual trust and co-operation'. When dealing with matters which are the subject of an early warning notice, the emphasis should be on agreeing the steps required to address the matter rather than allocating blame.
Certainly ignoring early warning notices is a dangerous game. Apart from a possible breach of clause 10, any compensation event that may follow is likely to be costlier to the client than if the matter had been dealt with at the outset.
But remember there is no direct link between early warning notices and compensation events. An early warning notice might not lead to a compensation event and a compensation event might occur without an early warning notice.
Some of the confusion around early warning notices can be accounted for by people having grown up within an adversarial contracting culture. Such culture should be discarded when using NEC.
This article was written by Rudi Klein, NEC Users’ Group President and Chief Executive at Specialist Engineering Contractors' (SEC) Group.
It was originally published here on 17 July 2017 by ICE.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.