NEC Option D: Target contract with bill of quantities
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the parties to a construction contract.
The Engineering and Construction Contract (ECC) is the most frequently used, and can be adopted on projects involving the construction of infrastructure or buildings. It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
It allows for 6 options:
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
Option D provides for a target cost with a bill of quantities:
- A target cost introduces a mechanism that enables the contractor, and/or the consultant team, to share in the benefits of cost savings, but also to bear some of the cost when there are cost overruns. This is typically shared in a pre-agreed proportion. For more information see: Target cost contract.
- A bill of quantities is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation. A bill of quantities can be prepared when the design is complete. For more information see: Bill of Quantities.
Option D includes core and secondary option clauses, the schedules of cost components, and contract data.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Bill of quantities.
- Conditions of contract.
- Construction contract.
- Contract documents.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
- NEC3.
- NEC4.
- Target contract.
- Target cost.
- Term contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
















