NEC Option D: Target contract with bill of quantities
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the parties to a construction contract.
The Engineering and Construction Contract (ECC) is the most frequently used, and can be adopted on projects involving the construction of infrastructure or buildings. It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
It allows for 6 options:
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
Option D provides for a target cost with a bill of quantities:
- A target cost introduces a mechanism that enables the contractor, and/or the consultant team, to share in the benefits of cost savings, but also to bear some of the cost when there are cost overruns. This is typically shared in a pre-agreed proportion. For more information see: Target cost contract.
- A bill of quantities is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation. A bill of quantities can be prepared when the design is complete. For more information see: Bill of Quantities.
Option D includes core and secondary option clauses, the schedules of cost components, and contract data.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Bill of quantities.
- Conditions of contract.
- Construction contract.
- Contract documents.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
- NEC3.
- NEC4.
- Target contract.
- Target cost.
- Term contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.
















