Loss and expense
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible, such as:
- Failure to give the contractor possession of the site.
- Failure to give the contractor access to and from the site.
- Delays in receiving instructions.
- Opening up works or testing works that then prove to have been carried out in accordance with the contract.
- Discrepancies in the contract documents.
- Disruption caused by works being carried out by the client.
- Failure by the client to supply goods or materials.
- Instructions relating to variations and expenditure of provisional sums.
- Inaccurate forecasting of works described by approximate quantities.
- Issues relating to CDM.
Claims may comprise costs resulting from disruption to the works or from delays to the works (prolongation).
The contractor must give written notice of a claim as soon as it becomes reasonably apparent that the regular progress of the works is being materially affected. This need not necessarily result in a delay to the completion date, and so claims for loss and expense and claims for extensions of time do not necessarily always run together.
Claims are restricted to 'direct' loss and expense and so 'consequential losses' (such as lost production) are generally excluded. Direct losses are those that 'flow naturally' from the breach of contract.
There is disparity between contract types about whether items such as head office overheads can be included in claims for loss and expense, and some court rulings have allowed such claims. If there are specific consequential losses which the parties to the contract wish to exclude, it may be prudent therefore to state these explicitly within the contract.
NB: The New Engineering Contract (NEC3) contains provision for the contractor to claim payment for 'compensation events' rather than loss and expense.
[edit] Related articles on Designing Buildings
- Business interruption cover under COVID-19.
- Causes of construction disputes.
- Civil procedure rules.
- Concurrent delay.
- Consequential loss.
- Contract claims.
- Contractual right.
- Cost overruns.
- Defects.
- Dispute resolution.
- Disruption claims in construction.
- Extension of time.
- Force majeure.
- Frustration.
- Head office overheads.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Liquidated damages.
- Named specialist work.
- Payment for extra work.
- Professional indemnity insurance.
- Profit and overheads.
- Prolongation.
- Provisional sums.
- Relevant event.
- Right to payment.
- The distinction between liquidated damages clauses and penalty clauses.
- Variations.
- What is a default?
[edit] External references
- Ascertaining Loss and Expense RICS: ISBN 978 1 78321 114 2
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Comments
According to JCT - Standard Building Contract , in Article 4.23 ...if Contractor incurs or likely to incur loss and expense for which he would not be reimbursed under any provision in these Conditions due to regular progress of Works or any part of them has been or is likely to be materially affected by any of the Relevant matters the Contractor may make an application to the Architect/Contract Administrator. If Architect is of the opinion that regular progress has been or likely to be materially affected ... issues a variation instruction.
in 4.24, a Relevant Matter is described to include the matter described above which is not initiated by Architect directly.
In 5.2, it is mentioned in text, Variations required by direct Architect's instructions as identical to ones (first encountered by Contractor as "differing site conditions" and brought to Architects attention) subsequently sanctioned by Architect in writing ( as a valid variation).
Thus, as opposed to many articles about JCT's being mute about "unforeseeable ground conditions") JCT includes "unforeseeable or differing site conditions clause " as a loss and expense item. Variation is normally considered as a modification of design, quality or quantity of Works instructed by Architect. For unforeseeable ground conditions, It is requested by Contractor first and then, ascertained and instructed by Architect as variation. If it is not instructed, it is a claim.
Therefore, please include "differing site conditions" as a loss and expense item in your list. It is like this in all English and American standard contracts except fidic silver book. This will make your list meaningful and complete.
Thankyou for your comment and just to clarify. Are you agreeing with the two statements below ?
'Unforeseen Ground Conditions: An example of how the NEC Contract form is more balanced is that NEC Contracts provide that the discovery of unexpected ground conditions, which even an experienced Contractor could not have foreseen at the date of the contract, constitutes a Compensation Event. JCT Contracts have no equivalent clause, which therefore mean that the risk for unexpected ground conditions on site is a Contractor’s Risk and the discovery of any unexpected ground conditions will normally mean the Contractor has no entitlement to an extension of time for completion of the works or any additional cost.' (source https://c-link.com/blog/jct-vs-nec/)
'Unexpected Ground Conditions: NEC Clause 60.1(12) provides that the discovery of unexpected ground conditions, which an experienced Contractor would have judged, at the date of the contract, had such a small chance of occurring that it would have been unreasonable to allow for them, constitutes a Compensation Event.
The JCT suite of contracts has no equivalent clause meaning that the risk of unexpected ground conditions on site is a Contractor's risk and that the discovery of any unexpected ground conditions will not normally entitle a Contractor to any extension of time for the completion of the works or any additional costs." (source:https://www.bevanbrittan.com/insights/articles/2017/jct-relevant-events-v-nec-compensation-events/)
in that if the contractor acts independently without written approval from the architect as a variation then it is not a cause for loss or expense. However if the Architect accepts and approves the unexpected ground conditions as a variation an issues this then it is a cause for loss or expense ?
I do note though that page 597-600 of Construction Law By Julian Bailey (pages can be found by ecosia or google search)
'UNFORSEEN SITE CONDITIONS 97'
8.37 notes that differing project types will have differing risks associated with site conditions.
8.38 notes that allocating of such risks will depend of the relationship between parties.
8.39 notes it is not uncommon for contracts to expressly allow contractors to claim loss and expense. However it also states within certain time periods state in the contract.
8.40 Deals with the definition of if it was reasonably foreseeable
8.41 The contractors responsibly for investigating site conditions.
8.42 Discusses that having investigated, the contract may infer the risk to the contractor ( or make allowances otherwise)
So in summary it rests on if the request by Contractor is instructed by Architect as a variation but if not instructed, it's allowance as a claim will depend on the specifics stated in the contract and in the JCT standard they are not.
I'm therefore not sure if including this is appropriate because it would be based on the approval of the variation from the Architect rather than if you like directly as an item, but happy to hear a if anything has been missed here. Perhaps it could be added so long as the above assumptions are also added for reference (but this may complicate things somewhat?). Is that a reasonable understanding and approach ?