International research into the causes of delays on construction projects
Contents |
[edit] Introduction
Delay in construction was described by Salunkhe and Patil (2014) as, “the time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project”.
Vyas (2013) stated that delay causes stress to project participants who tend to negate the effect of the delay either by accelerating the work process or by extending the project duration (Aibinu and Jagboro 2002). However, this is not without consequences, with impacts including; cost overrun, dispute, arbitration and litigation and even total abandonment (Salunkhe and Patil 2014; Aibinu and Jagboro 2002).
Delay is very common in construction projects across the world (Assaf and Al-Hejji 2005; Choudhury 2004) and is recognised as a global phenomenon occurring both in developed and developing countries (Salunkhe and Patil 2014). In the United Kingdom, the National Audit Office (2001) found that seventy percent of government construction projects experienced delay. Similarly, Assaf and Al-Hejji (2006) in their research found that about seventy percent of the projects in Saudi Arabia experienced time overruns, and this is supported by other reports from around the world (Aibinu and Jagboro 2002; Odeyinka and Yusif 1997).
[edit] International research
Researchers have identified a number of factors causing delays common to projects regardless of type and region.
Odeyinka and Yusif (1997) argued based on their research in Nigeria that causes of delay resulting from participant behaviour included; variation orders, slow decision-making, financial issues, material management problems, planning and scheduling problems, inadequate site inspection, equipment management problems and shortage of manpower. They also identified factors that cause delay that were not caused by the project participants, including; inclement weather, acts of god and so on. Similar causes of delay were identified by Odeyinka and Yusif (1997), Zayyana et al. (2014) in their research in Malaysia. Kaming et al. (2007) identified corresponding factors in Indonesia and so on.
Assaf et al. (2006) in their research in Saudi Arabia identified eight common factors causing delay, including; design changes, delay in drawings, slow contractor’s pace, poor relationships between the project participants, financial issues, slow decision-making and labour issues.
Sambasivan and Soon (2006) research into construction projects in Malaysia identified lack of communication, equipment availability and failure, inadequate contractor’s experience, labour issues, poor site management, material shortage, planning and scheduling problems and inadequate finance. Kaming et al. (2007) in Indonesia, Ubaid (1991), Al-barak (1993) also identified these factors.
Vyas (2013) in his research on construction projects in India identified safety, equipment and daily targets as some of the factors that caused delay. Likewise Al-Momani (2000) on his research in Jordan highlighted the main causes of delay as; design variation orders, weather, site conditions, late deliveries, financial issues and increases in quantity.
Noulmanee et al. (2000) investigated delay factors on highways construction in Thailand and concluded that the main causes were; inadequacy of sub-contractors, organisations lacking sufficient resources, incomplete and unclear drawings and deficiencies between consultants and contractors.
Chan and Kumaraswamy (1997) argued that the five principal and common causes of delays were; poor site management and supervision, unforeseen ground conditions, low speed of decision making involving all project teams, client-initiated variations and variations. Similarly, Odeh and Battaineh (2000) identified; owner interference, inadequate contractor experience, financing and payments, labour productivity, slow decision making, improper planning, and subcontractor performance.
Other research includes Ellis and Thomas (2002) on Highway construction in USA, Sun et al. (2004) on construction projects in the UK, Koukshi et al. (2005) on residential projects in Kuwait, Motaleb and Kishk (2013) on construction in UAE, Yang (2010) on construction projects in Taiwan, Kaliba et al (2009) on road projects in Zambia, Long (2008) on construction projects in Vietnam, Ahmed et al (2003) on building projects in USA, United Nation Development (2010) on construction projects in Iraq and Tumi et al (2009) on construction projects in Libya.
[edit] Summary
It is apparent that the causes of delay in construction revolve around certain universal factors:
- Design changes.
- Financial issues.
- Variation orders.
- Slow decision-making.
- Planning and scheduling problems.
- Material management problems.
- Poor site inspection.
- Shortages in labour.
- Delays in drawing.
- Slow contractor’s pace.
- Relationships between project participants.
- Unforeseen conditions.
- Design errors.
- Inadequate contractor experience.
See also: Delays on construction projects.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Compensation event.
- Concurrent delay.
- Construction disputes.
- Delay on construction projects.
- Dispute resolution.
- Extension of time.
- Modernising construction.
- Lead times.
- Liquidated damages.
- Loss and expense.
- Pressing pause to avoid errors.
- Programme for building design and construction
- Relevant event.
- Relevant event v relevant matter.
- Relevant matter.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.