International research into the causes of delays on construction projects
Contents |
[edit] Introduction
Delay in construction was described by Salunkhe and Patil (2014) as, “the time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project”.
Vyas (2013) stated that delay causes stress to project participants who tend to negate the effect of the delay either by accelerating the work process or by extending the project duration (Aibinu and Jagboro 2002). However, this is not without consequences, with impacts including; cost overrun, dispute, arbitration and litigation and even total abandonment (Salunkhe and Patil 2014; Aibinu and Jagboro 2002).
Delay is very common in construction projects across the world (Assaf and Al-Hejji 2005; Choudhury 2004) and is recognised as a global phenomenon occurring both in developed and developing countries (Salunkhe and Patil 2014). In the United Kingdom, the National Audit Office (2001) found that seventy percent of government construction projects experienced delay. Similarly, Assaf and Al-Hejji (2006) in their research found that about seventy percent of the projects in Saudi Arabia experienced time overruns, and this is supported by other reports from around the world (Aibinu and Jagboro 2002; Odeyinka and Yusif 1997).
[edit] International research
Researchers have identified a number of factors causing delays common to projects regardless of type and region.
Odeyinka and Yusif (1997) argued based on their research in Nigeria that causes of delay resulting from participant behaviour included; variation orders, slow decision-making, financial issues, material management problems, planning and scheduling problems, inadequate site inspection, equipment management problems and shortage of manpower. They also identified factors that cause delay that were not caused by the project participants, including; inclement weather, acts of god and so on. Similar causes of delay were identified by Odeyinka and Yusif (1997), Zayyana et al. (2014) in their research in Malaysia. Kaming et al. (2007) identified corresponding factors in Indonesia and so on.
Assaf et al. (2006) in their research in Saudi Arabia identified eight common factors causing delay, including; design changes, delay in drawings, slow contractor’s pace, poor relationships between the project participants, financial issues, slow decision-making and labour issues.
Sambasivan and Soon (2006) research into construction projects in Malaysia identified lack of communication, equipment availability and failure, inadequate contractor’s experience, labour issues, poor site management, material shortage, planning and scheduling problems and inadequate finance. Kaming et al. (2007) in Indonesia, Ubaid (1991), Al-barak (1993) also identified these factors.
Vyas (2013) in his research on construction projects in India identified safety, equipment and daily targets as some of the factors that caused delay. Likewise Al-Momani (2000) on his research in Jordan highlighted the main causes of delay as; design variation orders, weather, site conditions, late deliveries, financial issues and increases in quantity.
Noulmanee et al. (2000) investigated delay factors on highways construction in Thailand and concluded that the main causes were; inadequacy of sub-contractors, organisations lacking sufficient resources, incomplete and unclear drawings and deficiencies between consultants and contractors.
Chan and Kumaraswamy (1997) argued that the five principal and common causes of delays were; poor site management and supervision, unforeseen ground conditions, low speed of decision making involving all project teams, client-initiated variations and variations. Similarly, Odeh and Battaineh (2000) identified; owner interference, inadequate contractor experience, financing and payments, labour productivity, slow decision making, improper planning, and subcontractor performance.
Other research includes Ellis and Thomas (2002) on Highway construction in USA, Sun et al. (2004) on construction projects in the UK, Koukshi et al. (2005) on residential projects in Kuwait, Motaleb and Kishk (2013) on construction in UAE, Yang (2010) on construction projects in Taiwan, Kaliba et al (2009) on road projects in Zambia, Long (2008) on construction projects in Vietnam, Ahmed et al (2003) on building projects in USA, United Nation Development (2010) on construction projects in Iraq and Tumi et al (2009) on construction projects in Libya.
[edit] Summary
It is apparent that the causes of delay in construction revolve around certain universal factors:
- Design changes.
- Financial issues.
- Variation orders.
- Slow decision-making.
- Planning and scheduling problems.
- Material management problems.
- Poor site inspection.
- Shortages in labour.
- Delays in drawing.
- Slow contractor’s pace.
- Relationships between project participants.
- Unforeseen conditions.
- Design errors.
- Inadequate contractor experience.
See also: Delays on construction projects.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Compensation event.
- Concurrent delay.
- Construction disputes.
- Delay on construction projects.
- Dispute resolution.
- Extension of time.
- Modernising construction.
- Lead times.
- Liquidated damages.
- Loss and expense.
- Pressing pause to avoid errors.
- Programme for building design and construction
- Relevant event.
- Relevant event v relevant matter.
- Relevant matter.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























