Design and build: occupation and defects liability period
The occupation and defects liability period takes place after the client has taken possession of the development for occupation. During this stage, any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, and the contractor no longer has possession of the site, close co-operation is required between the contractor and the client so as so not to disturb occupants, whose activities will take priority over work required to rectify defects.
[edit] Starting the work stage.
The employer's agent arranges a start-up meeting to plan the work stage.
The client may identify a requirement to appoint additional independent client advisers (such as site inspectors) in particular if the consultant team has been novated or switched to the contractor.
[edit] Rectifying defects.
If the contract allows, the employer's agent may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the employer's agent. On large projects the contractor may set up a hot desk for responding to any complaints or to provide assistance required by the incoming occupants. The employer's agent instructs the contractor to rectify the defects and the contractor and client agree a programme for rectifying defects in a way that minimises disruption to the client.
The contractor rectifies the defects.
If rectification works are significant, it may be necessary to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to amend to the health and safety file.
If any amounts are due to the contractor, they prepares interim applications for payment (or the client might issue payment notices, depending on the provisions of the contract).
The employer's agent checks applications for payment and issues payments notice to the contractor. The notices must be issued within five days of the dates for payment set out in the contract. If the client intends to pay less than the notified amount, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client pays the contractor by the final date for payment.
At the end of the defects liability period, the employer's agent arranges inspections of the works and prepares a schedule of defects which is issued to the contractor. The employer's agent agrees the programme for rectification of items on the schedule of defects with the contractor, which should in any event be rectified within a reasonable time.
The contractor rectifies items listed on the schedules of defects and informs the employer's agent. The employer's agent arranges final inspections of the works and if satisfied issues a statement confirming that the defects have been made good.
If a site waste management plan has been prepared, the contractor may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
[edit] Issuing the final statement.
The employer's agent co-ordinates preparation of a final report.
The contractor co-ordinates preparation of the final statement (and supporting information) for the employer's agent.
The employer's agent checks the final statement and gives notice to the contractor of the amount to be paid. If the final statement is not disputed it becomes conclusive that all items identified in the employer's requirements as for the 'approval' of the client are be deemed to have been approved. It is also conclusive regarding extensions of time and claims for loss and/or expense.
The client makes payment by the final date for payment (including the release of any remaining retention).
Issuing the final certificate may signify the end of independent client advisers appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.