Cesspool
A cesspool is an underground tank used to collect wastewater and sewage. It will typically have a manhole for access, but does not have an outlet and does not discharge any of its contents. Unlike a septic tank, a cesspool does not process or treat wastewater and sewage it simply stores it.
Cesspools are sometimes referred to as cesspits, although both terms can also be used to refer to a underground chamber that is not sealed at the bottom so as to allow liquid to seep into the surrounding ground (commonly referred to as a soak pit). This has not been permitted since the introduction of the Public Health Act 1936.
Cesspools should be inspected fortnightly and the level checked (an automatic alarm may be installed). The contents of the cesspool must be removed regularly (typically every month depending on size and usage – much more frequently than an equivalent septic tank) by a licensed waste handler using a vacuum tanker. This can be a significant expense.
Cesspools are generally only installed at properties that are not connected to the public sewer network and that do not have suitable ground to provide a septic drain field (required for the installation of a septic tank), or at locations such as campsites where chemical toilets are emptied that might prevent a septic tank from functioning correctly.
Permits are not required for cesspools, and they do not have to comply with the general binding rules that apply to septic tanks. However, planning permission and building regulations approval is needed to install a cesspool.
Requirements for the design, construction and maintenance of cesspools are set out in Approved Document H of the building regulations, which permits cesspools were the installation of a septic tank is not reasonably practicable.
Cesspools should be at least 7m from habitable parts of a building, preferably downslope, and must be adequately ventilated. They should be within 30m of vehiclular access. They should have a capacity of at least 18,000 litres for two users and a further 6,800 litres for each additional user. A filling rate of 150 litres per person per day is assumed when estimating filling rates.
A durable notice must be fixed in the building associated with the cesspool, providing information about its maintenance.
Cesspools are generally manufactured from glass reinforced plastic, polyethylene or steel, or constructed from brickwork or concrete. Older cesspools of masonry construction may have deteriorated over time, resulting in leaks or weaknesses that can lead to collapse. Cesspools should be inspected periodically by a suitably qualified engineer to ensure they remain sound.
If a cesspool does not fill as quickly as expected, or if the level suddenly drops, it should be inspected for possible leaks. Allowing a cesspool to overflow or leak is an offence under the Public Health Act 1936, and allowing a cesspool to pollute a watercourse is an offence under the Water Recourses Act 1991.
[edit] Related articles on Designing Buildings Wiki
- Air admittance valve.
- Approved Document H.
- Difference between drains and sewers.
- Drainage stack.
- Drainage.
- Drains.
- Grease management.
- Miasma theory.
- Plumbing.
- Private sewer.
- Public sewer.
- Safe working in drains and sewers.
- Sanitary pipework.
- Sanitaryware.
- Section 102 existing sewer adoption.
- Section 104 new sewer adoption.
- Septic tank
- Sewer.
- Soil vent pipe.
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.