Last edited 07 Oct 2026

Building safety levy

Contents

[edit] Introduction

The Building Safety Levy is a charge on new residential development in England. It came into operation on 1 October 2026. The money raised helps pay to fix historical building safety defects, such as unsafe cladding, so that leaseholders and taxpayers do not have to.

The levy applies to building control applications and initial notices submitted on or after 1 October 2026. It is charged per square metre of new residential floorspace, at a rate set for each local authority area, and must be paid before a completion certificate can be issued. Local authorities collect it.

The levy applies in England only. Wales, Scotland and Northern Ireland are not covered.

[edit] Background and history

The levy is part of the response to the Grenfell Tower fire of 14 June 2017. The Building Safety Act 2022 gives the Secretary of State power to set up a levy on new residential buildings (section 58). Details were left to secondary legislation.

The levy sits alongside other measures that make the housebuilding industry pay towards remediation. These include the Residential Property Developer Tax (RPDT), a 4% tax on large developers' profits introduced in April 2022, and the developer remediation contract, under which major housebuilders agreed to fix buildings they developed.

The start date was delayed to give local authorities, building control bodies and developers about 18 months to prepare. The government's revenue target is £3.4 billion. This is the sum still needed for remediation once public funding, industry pledges and contractual obligations are taken into account.

[edit] How the levy works

[edit] What is charged

The levy applies to new dwellings, purpose-built student accommodation (PBSA) and changes of use to residential. It applies regardless of building height, so it is not limited to higher-risk buildings. The person who pays is the client named on the building control application or initial notice.

[edit] Exemptions

Small developments are exempt. A development is only charged if it is a major residential development: 10 or more new dwellings, or 30 or more PBSA bedspaces. Other exemptions include:

[edit] Rates

The levy is charged per square metre of gross internal area (GIA) of chargeable floorspace, including a share of communal areas. Rates are set by government for each local authority area and listed in the regulations. Higher rates apply where house prices are higher. Standard rates range from £6.35/m² in County Durham to £50.17/m² in Kensington and Chelsea.

Development on previously developed (brownfield) land is charged at half the standard rate. The 2026 amendment regulations confirmed that hard standing and car parks count as previously developed land. PBSA is charged at the same rate as other dwellings.

[edit] Collection

The charge is recalculated if the works change, and any overpayment is refunded. Building control bodies have to check with the collecting authority before issuing a completion certificate. This applies whether building control is provided by the local authority, a registered building control approver (RBCA) or the Building Safety Regulator.

[edit] Issues and criticism

The main concern is the effect on housing supply. In March 2025, the Home Builders Federation and a large number of housebuilders wrote to the Chancellor asking for the levy to be suspended. They made these points:

The government went ahead with the levy but delayed its start to October 2026. Supporters argue that developers, rather than leaseholders or taxpayers, should meet the remaining remediation costs. The exemptions for small sites, social housing and brownfield land are intended to soften the impact on supply.

[edit] Further information

Guidance and legislation

Consultations

Industry comment

[edit] Related articles on Designing Buildings

.

Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again