Building permit
In the United States, a building permit (or construction permit) is an authorisation that must be obtained before some types of construction works can begin. Towns, municipalities and other jurisdictions use building permits to enforce building codes that apply on a local level, ensuring that construction works comply with minimum standards.
The English equivalent is building regulations approval.
There are several reasons why a building permit should be obtained:
- Doing so is a legal requirement and failing to do so can result in a fine.
- It ensures contractors use safe and legal construction materials, methods and techniques.
- Insurance companies may not honour policies if building work is done without a permit.
- It may be difficult to but or sell a property without a permit.
Whether or not a building permit is required for certain types of work, and the associated fees, differ depending on the local state or municipality rules. For example, an area that is more prone to seismic activity or extreme weather conditions may require a building permit for a type of work that does not require one elsewhere.
Generally, all new construction work, work done to change the use of a structure and demolition work will require a permit. Plumbing, electrical and mechanical work can sometimes be included in an overall building permit, or sometimes may require a separate permit.
Some lesser types of work may differ depending on local requirements; for example, decking, installing a shed, installing siding and so on. Local building departments should be consulted before beginning work of this nature to confirm whether or not a permit is required. Minor works such as simple repairs, decoration, replacing doors and windows, generally do not require a permit.
It is usual for a contractor to take responsibility for obtaining a permit as they are generally familiar with the application process and are liable for complying with its requirements. If a building owner wishes to do work themselves, they must obtain the permit and assume responsibility for complying with the building codes.
When applying for a permit, detailed plans and calculations will need to be submitted, with the complexity of the project determining the detail and scope required.
A permit is usually valid for six months after it has been issued, meaning that the work must begin within this time. The permit remains valid throughout the span of the project until completion, however, it may be necessary to obtain an extension if work is suspended for longer than six months at a time.
If standard plans are agreed to, then pre-approved permits can sometimes be obtained. For example, if the structure or works conform to a basic design provided by the municipality then as long as the plans are followed, there is no need to submit project-specific plans. Prefabricated works that require simple assembly can obtain a building permit from the submission of the documents provided by the manufacturer.
Retrospective applications for a building permit can be accepted if there is an urgent requirement to continue with the works before an inspector can attend (for example if there are safety concerns). Documentary evidence of the work (e.g. photographs, videos, etc.), will usually be required.
If significant changes are proposed after a permit has been obtained, the building department should be consulted.
[edit] Related articles on Designing Buildings Wiki
- Approval of conditions on a planning permission.
- Building codes.
- Construction site inspection.
- International building code (IBC).
- Permit.
- Permit to work for construction.
- Permitted development.
- Planning condition.
- Planning permission.
- Risk assessment.
- What approvals are needed before construction begins.
Featured articles and news
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.























