Permit to work for construction
Permit to work (PTW) systems are formal procedures used to control activities that are considered high-risk. Permits only allow authorised personnel to perform those activities at specified times and in a way set out in the permit and referenced documents.
A permit to work might be required for activities such as:
- Electrical works.
- Hot works.
- Excavation.
- Lone working.
- Lifting operations.
- Work in confined spaces.
- Work to high risk spaces such as laboratories, or industrial plant.
- Work at height.
- Work to roofs.
- Temporary works.
- Work with asbestos.
- Demolition.
- Work to high pressure systems.
A permit to work system should:
- Only allow permits to be issued by authorised, competent personnel.
- Prevent high-risk work being carried out without a risk assessment having been undertaken.
- Consider whether any other work will impact on, or be impacted by, the permitted work.
- Ensure control measures and supervision are in place.
- Ensure method statements and emergency procedures are prepared.
- Ensure work is checked and returned to a safe state.
- Provide information to other parties that might be affected by the work.
- Include a system for handing back and cancelling permits.
Permits should:
- Describe the work and its location.
- Provide information about foreseeable risks.
- Provide information necessary for working safely.
- Set out requirements for personal protective equipment.
- Set out the time when the work can be carried out.
- Provide information about other permits.
Issuing permits to work can be a complicated and time-consuming process and so adequate notice should be given before a permit to work is required.
Permit to work systems do not in themselves make activities safer, this is only possible through the implementation of the correct procedures. It is important therefore that systems not box-ticking exercises, that they are explained at site inductions and that they are continuously monitored, reviewed and kept up to date.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines a Permit-to-Work system as: ‘A documented management system that includes specific processes to record and authorise tasks to be carried out by designated parties, including employees and contractors, so that they are aware of their risks and responsibilities.’
[edit] Related articles on Designing Buildings
- Asbestos.
- CDM.
- Demolition.
- Gangmaster.
- Health and Safety.
- Method statement.
- Permit.
- Personal protective equipment
- Risk assessment.
- Safe2Torch.
- Site induction.
- Site records and registers.
[edit] External references
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.


















