Force majeure in construction
The term ‘force majeure’ comes from French law, where it translates as 'superior force' (as opposed to ‘vis majeure’ or ‘vis major’ which refers to an act of God). Whilst in France, the term has a defined legal meaning, in English law it does not, and it is dealt with in different ways by different forms of contract.
Very broadly, it relates to exceptional, unforeseen events or circumstances that are beyond the reasonable control of a party to a contract and which prevent or impede performance of their obligations under the contract. Generally it cannot be an event that the party could reasonably have avoided or overcome, or an event attributable to the other party.
Clauses referring to force majeure attempt to set out the circumstances to which the term applies to and prescribe how such situations should be treated. Depending on the provisions of the contract, the following may be considered to constitute force majeure:
- Unforeseen changes to legislation.
- Wars and other hostilities (such as terrorism).
- Fires.
- Exceptionally adverse weather.
- Civil unrest, such as riots or revolution.
- Strikes (other than by the contractor or subcontractors).
- Natural catastrophes such as earthquakes, floods and volcanoes.
- Epidemics or pandemics.
In some contracts, force majuere is considered a 'relevant event', that may allow the contractor to claim an extension of time if they have been prevented or impeded from performing their obligations under the contract. Although, if the contractor has continued to perform their duties, despite the occurrence, they may not be able to make a claim.
As these conditions tend not to be defined, it can be difficult to determine whether they have arisen or not. For example, when does a virulent virus constitute an epidemic? This has become particularly significant in recent years due to the increasing number of exceptionally adverse weather events (in particular flooding), as well events such as foot and mouth, swine flu and restrictions on air travel due to volcanic ash clouds.
Whilst clients will generally accept the contractor cannot perform their duties under the contract where there is genuine force majeure, problems arise when the client believes the contractor is unnecessarily claiming force majeure for commercial gain and that the situation could have been foreseen, avoided or mitigated. Disputed claims are particularly common in relation to exceptionally adverse weather as the term is not always defined.
Force majeure clauses need to be flexible enough to cover events which are by their very definition are unforeseeable, but specific enough to prevent disputes arising.
Some forms of construction no longer use the phrase force majeure, but instead include clauses to deal with the specific circumstances that might arise.
In situations where a contractual obligation becomes incapable of being performed, the occurrence might be considered to be a 'frustration event' resulting in termination of the contract. Frustration occurs when circumstances that are not the fault of either party mean it is impossible to continue with the contract. The contract will come to an end without any party being considered to be in breach.
For more information, see Frustration.
NB The Chartered Institute of Procurement & Supply (CIPS) Glossary of procurement terms, defines a force majeure as: ‘Circumstances that cannot be foreseen which prevent a contract from being fulfilled.’
[edit] Related articles on Designing Buildings
- Breach of contract.
- Clear contracts during uncertain times.
- Compensation event.
- Concurrent delay.
- Consequential loss.
- Coronavirus and force majeure.
- Exculpatory clause.
- Exigency.
- Extension of time.
- Neutral event.
- Frustration.
- Liquidated damages.
- Loss and expense.
- Relevant event.
- Termination.
[edit] External references
- Matsoukis v Priestman & Co (1915).
- Lebeaupin v Crispin (1920).
Featured articles and news
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.