Force majeure in construction
The term ‘force majeure’ comes from French law, where it translates as 'superior force' (as opposed to ‘vis majeure’ or ‘vis major’ which refers to an act of God). Whilst in France, the term has a defined legal meaning, in English law it does not, and it is dealt with in different ways by different forms of contract.
Very broadly, it relates to exceptional, unforeseen events or circumstances that are beyond the reasonable control of a party to a contract and which prevent or impede performance of their obligations under the contract. Generally it cannot be an event that the party could reasonably have avoided or overcome, or an event attributable to the other party.
Clauses referring to force majeure attempt to set out the circumstances to which the term applies to and prescribe how such situations should be treated. Depending on the provisions of the contract, the following may be considered to constitute force majeure:
- Unforeseen changes to legislation.
- Wars and other hostilities (such as terrorism).
- Fires.
- Exceptionally adverse weather.
- Civil unrest, such as riots or revolution.
- Strikes (other than by the contractor or subcontractors).
- Natural catastrophes such as earthquakes, floods and volcanoes.
- Epidemics or pandemics.
In some contracts, force majuere is considered a 'relevant event', that may allow the contractor to claim an extension of time if they have been prevented or impeded from performing their obligations under the contract. Although, if the contractor has continued to perform their duties, despite the occurrence, they may not be able to make a claim.
As these conditions tend not to be defined, it can be difficult to determine whether they have arisen or not. For example, when does a virulent virus constitute an epidemic? This has become particularly significant in recent years due to the increasing number of exceptionally adverse weather events (in particular flooding), as well events such as foot and mouth, swine flu and restrictions on air travel due to volcanic ash clouds.
Whilst clients will generally accept the contractor cannot perform their duties under the contract where there is genuine force majeure, problems arise when the client believes the contractor is unnecessarily claiming force majeure for commercial gain and that the situation could have been foreseen, avoided or mitigated. Disputed claims are particularly common in relation to exceptionally adverse weather as the term is not always defined.
Force majeure clauses need to be flexible enough to cover events which are by their very definition are unforeseeable, but specific enough to prevent disputes arising.
Some forms of construction no longer use the phrase force majeure, but instead include clauses to deal with the specific circumstances that might arise.
In situations where a contractual obligation becomes incapable of being performed, the occurrence might be considered to be a 'frustration event' resulting in termination of the contract. Frustration occurs when circumstances that are not the fault of either party mean it is impossible to continue with the contract. The contract will come to an end without any party being considered to be in breach.
For more information, see Frustration.
NB The Chartered Institute of Procurement & Supply (CIPS) Glossary of procurement terms, defines a force majeure as: ‘Circumstances that cannot be foreseen which prevent a contract from being fulfilled.’
[edit] Related articles on Designing Buildings Wiki
- Breach of contract.
- Clear contracts during uncertain times.
- Compensation event.
- Concurrent delay.
- Consequential loss.
- Coronavirus and force majeure.
- Exigency.
- Extension of time.
- Neutral event.
- Frustration.
- Liquidated damages.
- Loss and expense.
- Relevant event.
- Termination.
[edit] External references
- Matsoukis v Priestman & Co (1915).
- Lebeaupin v Crispin (1920).
Featured articles and news
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.