Tender price
A tender is a submission made by a prospective supplier (the ‘tenderer’) in response to an invitation to tender (ITT). It makes an offer for the supply of goods or services. A tender price is therefore the price supplied by the tenderer to the client for the supply of those goods or services.
The tender price is usually based on information about the project that has been supplied by the client in the ITT documents. These documents are usually as comprehensive as possible to allow the formulation of accurate tender prices and may include:
- A letter of invitation to tender.
- The form of tender.
- Preliminaries.
- The form of contract.
- A tender pricing document.
- A drawing schedule.
- Design drawings.
- Specifications.
If the client’s documents to not adequately describe the project they could lead to unrealistic tender submissions.
When suppliers submit their tender price, it will represent the price at which they have decided to do the works or supply the goods or services, along with proposals for how the client’s requirements will be satisfied - if these have been requested.
The tender price supplied will be presented in a way set out in the tender pricing document A tender pricing document sets out the way the client wishes to review the breakdown of overall tender prices provided by the tendering contractors.
Because the tender pricing document is designed to allow easy, like-for-like comparisons between the tender prices submitted by the various suppliers, it can reveal to the client where the best value for money lies among the tenderers, identifies significant differences as well as areas where savings can be made or negotiations undertaken.
[edit] Tender price indices
Tender price indices allow tenderers and clients to see how tender prices for building contracts are changing. The indices may be used in estimating, cost-checking and fee negotiation with reference to particular sectors e.g private housing, commercial work etc.
An example is the Tender Price Index of Public Sector Building Non-Housing (or PUBSEC) that is produced by the Building Cost Information Service (BCIS) on behalf of the Department of Business Innovation and Skills (now called the Department for Business, Energy and Industrial Strategy (BEIS).
PUBSEC is based on rates of measured work contained in Bills of Quantities or quantified schedules for accepted tenders. The index, published quarterly, is accurate as it is based only on projects where the procurement process has produced ‘measured work’ documents.
For more information see: Construction price and cost indices.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Auction theory.
- Best value.
- Common mistakes in construction tenders.
- Competitive tender.
- Construction contract.
- Construction price and cost indices.
- Due diligence when selecting contractors or subcontractors.
- Form of tender.
- How to prepare tender documents.
- Pre-tender Interviews.
- Margin.
- Mid-tender Interviews.
- Pre-qualification questionnaire.
- Private Finance Initiative.
- Procurement route.
- Tender evaluation.
- Tender processes.
- Things to avoid when tendering.
- Two stage tender.
- Invitation to tender.
- Tender documentation.
- Tender return slip.
- Tender settlement meeting.
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.