Construction progress report
Construction progress reports are prepared regularly (often monthly) by the contract administrator during the construction phase and issued to the client. They will generally be a summary of the reports received and discussions held at construction progress meetings.
Construction progress reports may be a combination of minutes of construction progress meetings and reports received during those meetings, with key issues highlighted in an accompanying cover note. Alternatively they may be a re-written version of that information prepared specifically to suit the client's requirements.
Construction progress reports might include:
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Weather reports.
- An assessment of any health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
Similar reports may be prepared on management contract projects in relation to works contractor progress.
[edit] Related articles on Designing Buildings Wiki
- Client.
- Construction progress meeting.
- Construction manager.
- Contractor.
- Contract administrator.
- Consultant team.
- Construction stage report.
- Earned value analysis.
- Employer's agent.
- Health and Safety.
- Management contractor.
- Progress of construction works.
- Project programme.
- Project manager.
- Project manager's report.
- Site meeting.
- Sub contractor.
- Warranties.
- Works contractor
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.


















Comments